Page 349 - Practical Power System and Protective Relays Commissioning
P. 349

344  Practical Power System and Protective Relays Commissioning































            FIGURE 20.4.8 Relay operating time test connection.

            Subchapter 20.5

            Transformer Protection Testing and

            Commissioning


            20.5.1 TRANSFORMER DIFFERENTIAL PROTECTION
            1. Open the tripping links of the relay and, if the circuit is energized, SC
               the secondary circuits of the CT at both sides of the power transformer
               and inject current in the relay side only, as shown in Fig. 20.5.1.
               Consider a power transformer of 500/220 kV, 500 MVA, Yy 0 .
            1. Close links: A, B, C in TB1.
            2. Close links: a, b, c in TB2.
            3. Open links: 1, 2, 3, 4 in TB1.
            4. Open links: 1, 2, 3, 4 in TB2.
               Inject currents are as shown in Fig. 20.5.1 and also connect the output
            tripping contacts of the relay to the test set as shown in Fig. 20.5.1.


            20.5.2 SECONDARY INJECTION TESTS
            1. Pickup test
   344   345   346   347   348   349   350   351   352   353   354