Page 84 - Materials Chemistry, Second Edition
P. 84

Ch002-P373623.qxd  3/22/07  5:27 PM  Page 65
                                                                Cleaner Production
                                                                     Feeding water  65


                          1    2     3    4    5    6    7    8



                                                                     Draining water
                                Kyoto bleaching unit before modification


                                                                     Feeding water


                          1    2     3    4    5    6    7    8



                                                                     Draining water
                                 Kyoto bleaching unit after modification

                FIGURE 2.2 Bleaching unit before and after modification

                     • Water and energy conservation: The factory was inspected to deter-
                       mine the sources of water and energy losses. It was found that the
                       pre-treatment and dyeing departments offered the greatest potential
                       for savings and efforts were focused in these areas as follows:
                       – Collection and reuse of steam condensate (equipment modifica-
                          tion): Around 20% of the steam being used in the different process-
                          ing departments is now being recovered in the form of condensate,
                          which is stored in a water collection tank and re-circulated to the
                          process water feed lines by means of pumps and piping network.
                       – Upgrade insulation of steam and hot water network (better process
                          control): In the pre-treatment department, the steam network was
                          assessed to identify areas of heat losses. This was shown to result
                          almost entirely from inadequate insulation. Once all necessary
                          insulation was completed, energy recovery consumption was
                          reduced, such that 6,576 million kcal of heat will be saved annually.
                       – Counter current flow (process control): In the eight washers of the
                          Kyoto bleaching unit range, the least contaminated water from the
                          final wash is recirculated 1–2 times in the preceding wash, before
                          being finally discharged. Using this approach, water is fed to three
                          wash units instead of eight as shown in Figure 2.2. This required
                          the installation of new pipelines, tanks, pumps, valves, and filters.
                       – Installation of automatic shut-off valves in bleaching ranges
                          (better process control): An evaluation of all bleaching ranges
                          revealed that process water and steam were being consumed even
   79   80   81   82   83   84   85   86   87   88   89