Page 260 - Water Engineering Hydraulics, Distribution and Treatment
P. 260

238
                                                   Water Distribution Systems: Modeling and Computer Applications
                                          Chapter 7
                                    two water mains, one in Town Highway #64 and the other in Elm
                                                                                       7.8
                                    Street. The following data were obtained:
                                                                                       within its water distribution network (Fig. 7.18). They want to deter-
                                                                                       mine the age and the chlorine concentration of the water as it exits
                                                                                       the system at different junctions. The water surface at the reservoir
                                    Town Highway #64 Hydrant Test
                                                                                       is 70 m.
                                    Static pressure:
                                                                      310.3 kPa
                                    Residual pressure:
                                                                      98.5 kPa at 32 L/s
                                                                                        R-1
                                    Elevation of pressure gauge:
                                                                      190 m
                                                                                                PMP-1
                                                                                            P-7
                                                                                                                              P-13
                                                                                                                                   J-9
                                    Elm Street Hydrant Test
                                                                                                  P-8
                                                                                                     J-5
                                                                                                            P-5
                                                                                                                     J-6
                                                                                                                         P-6
                                                                                               P-4
                                                                      413.7 kPa
                                    Static pressure:
                                                                                                                              J-7
                                    Residual pressure:
                                                                      319.3 kPa at 40 L/s
                                                                      191.5 m
                                    Elevation of pressure gauge:
                                                                                          P-1 J-4 A local water company is concerned with the water quality
                                                                                                    P-10             P-11    P-12
                                        The subdivision will connect to existing system mains in these
                                    streets at nodes J-8 and J-9. (Hint: Model the connection to an  J-1
                                    existing water main with a reservoir and a pump.)        P-2                        P-14
                                                                                                                              J-8
                                      1. What are the demands at each of the junction nodes? What is  J-2   P-3      J-3
                                        the total demand?                                           P-9
                                      2. Does the present water distribution system have enough capac-
                                        ity to supply the new subdivision?                           T-1
                                      3. Which connection to the existing main is supplying more  Figure 7.18 Schematic for Problem 7.8.
                                        water to the subdivision? Why?
                                      4. Are the proposed pipe sizes adequate to maintain velocities  Chlorine is injected into the system at the source of flow, R-1,
                                        between 0.15 and 2.44 m/s, and pressures of at least 140 kPa?  at a concentration of 1 mg/L. It has been determined through a series
                                      5. Would the subdivision have enough water if only one connec-  of bottle tests that the average bulk reaction rate of the chlorine in
                                        tion were used? If so, which one?              the system (including all pipes and tanks) is approximately –0.5 per
                                      6. What do you think are some possible pitfalls of modeling  day. Pump information and stepwise water demand pattern data are
                                        two connections to existing mains within the same system, as  as shown in Tables 7.28 and 7.29. Junction and pipe information
                                        opposed to modeling back to the water source?  are given in Tables 7.30 and 7.31.
                                    7.7  Use the pipe sizes given in Table 7.27 for the subdivision in
                                    Problem 7.6. City ordinances require that the pressure at the fire  Table 7.28  Pump information for Problem 7.8
                                    flow discharge and at other points in the distribution system cannot
                                                                                       Head (m)  Discharge (L/min)      Controls
                                    fall below 125 kPa during a fire flow of 34 L/s. (Hint: The total flow
                                    at the fire flow node does not need to include the baseline demand.)  40  0  Off if node T-1 above 103.5 m
                                                                                       35            3,000       On if node T-1 below 100.5 m
                                          Table 7.27  Pipe information for Problem 7.7  24           6,000
                                          Pipe label               Diameter (mm)
                                          P-1                          200
                                          P-2                          150             Table 7.29  Stepwise demand pattern data for Problem 7.8
                                          P-3                          150
                                                                                       Time from                  Time from
                                          P-4                          150
                                                                                       start (h)    Multiplier     start (h)   Multiplier
                                          P-5                          150
                                          P-6                          150             0              0.80          13           1.30
                                          P-7                          150             1              0.60          14           1.40
                                          P-8                          150             2              0.50          15           1.50
                                          P-9                          150             3              0.50          16           1.60
                                                                                       4              0.55          17           1.80
                                                                                       5              0.60          18           1.80
                                      1. If a residential fire occurs at J-7, would the current system be  6  0.80  19           1.40
                                        able to meet the fire flow requirements set by the city?  7   1.10          20           1.20
                                      2. If not, what can be done to increase the available flow to  8  1.50        21           1.00
                                        provide adequate fire flow to that hydrant?    9              1.40          22           0.90
                                                                                       10             1.30          23           0.80
                                      3. If a fire flow is placed at J-4, does the system meet the require-
                                                                                       11             1.40          24           0.80
                                        ments with the proposed improvements? Without the pro-
                                                                                       12             1.40
                                        posed improvements?
   255   256   257   258   259   260   261   262   263   264   265