Page 408 - Water and wastewater engineering
P. 408

SEDIMENTATION 10-25

          second stage. These flocculate with the preformed turbidity floc. After flocculation, the ballasted
          floc is settled in a high-rate settler, and the sludge is pumped to a hydrocyclone where the mic-
          rosand is recovered for reuse.
               The surface loading rate ranges from 35 to 62 m/h. The floc settling velocities are 20 to
          60 times greater than conventional sedimentation. This allows a reduction in detention time to
          between 9 and 10 minutes. The sludge contains 10 to 12 percent sand by weight.


            10-4  SEDIMENTATION BASIN DESIGN
            Rectangular tank and high-rate settlers are the primary focus of this discussion. Because ballasted
          sedimentation is a proprietary process, the design is under the control of the manufacturers. The
          design of this process will not be covered.

             Rectangular Sedimentation Basins
           At a minimum, to provide redundancy, two tanks are provided. These are placed together, in
          parallel, with a common wall. In general, four tanks are preferred (Willis, 2005). This provides
          maximum flexibility in operation over a wide range of flow rates with allowance for one unit be-
          ing out of service at the maximum flow rate. Four tanks, however, may result in an unacceptable
          capital cost.

            Inlet Zone.  The preferred arrangement is a direct connection between the flocculation basin
          and the settling tank. The diffuser wall between the two tanks is designed using the same proce-
          dure that was used for baffle walls in flocculation tanks (Chapter 6).
               When the flocculated water must be piped to the settling tank, the flow velocity commonly
          used is in the range of 0.15 to 0.6 m/s. This velocity must be reduced and the flow spread evenly
          over the cross section of the settling tank. A diffuser wall is the most effective way to accomplish
          this. The design process is the same as that used for baffle walls in flocculation tanks (Chapter 6).
              The diffuser wall is placed approximately 2 m downstream of the inlet pipe. The headloss
          through the holes should be 4 to 5 times the velocity head of the approaching flow. Port velocities
          typically must be about 0.20 to 0.30 m/s for sufficient headloss. The holes are about 0.10 to 0.20 m
          in diameter spaced about 0.25 to 0.60 m apart. They are evenly distributed on the wall. The lowest
          port should be about 0.6 m above the basin floor (Willis, 2005).

            Settling Zone.  Overflow rate is the primary design parameter for sizing the sedimentation ba-

          sin. Typical overflow rates are given in  Table 10-2 . These rates are usually conservative enough
          that the inlet zone does not have to be added to the length calculated for the settling zone. If the
          overflow rate is based on pilot studies, then the length of the inlet zone is added to the length
          calculated from the overflow rate.
              In theory the sedimentation basin depth [also called  side water depth  (SWD)] should not
          be a design parameter because removal efficiency is based on overflow rate. However, there is
          a practical minimum depth required for sludge removal equipment. In addition, depth may be a
          controlling parameter to limit flow-through velocities and/or scour of particles from the sludge
          blanket. Basins with mechanical sludge removal equipment are usually between 3 and 5 m deep
          (MWH, 2005, and Willis, 2005).
               To provide plug flow and minimize short circuiting, a minimum length to width ratio (L:W)
          of 4:1 is recommended. A preferred L:W is 6:1 (Kawamura, 2000).
   403   404   405   406   407   408   409   410   411   412   413