Page 329 -
P. 329

10 - PROJECT COMMUNICATIONS MANAGEMENT






                        •   Feedback from stakeholders. Information received from stakeholders concerning project operations is
                           distributed and used to modify or improve future performance of the project.
                        •   Lessons learned documentation. Documentation includes the causes of issues, reasoning behind
                           the corrective action chosen, and other types of lessons learned about communications management.
                           Lessons learned need to be documented and distributed so that it becomes part of the historical database
                           for both the project and the performing organization.


                   10.3 control communications


                     Control Communications is the process of monitoring and controlling communications throughout the entire
                   project life cycle to ensure the information needs of the project stakeholders are met. The key benefit of this process
                   is that it ensures an optimal information flow among all communication participants, at any moment in time. The
                   inputs, tools and techniques, and outputs of this process are depicted in Figure 10-7. Figure 10-8 depicts the data
                   flow diagram of the Control Communications process.
                                                                                                                          10

                                     Inputs            Tools & Techniques           Outputs

                              .1  Project management plan  .1  Information management    .1  Work performance
                              .2  Project communications    systems             information
                              .3  Issue log           .2  Expert judgment     .2  Change requests
                              .4  Work performance data  .3  Meetings         .3  Project management plan
                              .5  Organizational process                       updates
                                assets                                        .4  Project documents
                                                                               updates
                                                                              .5  Organizational process
                                                                               assets updates

                               Figure 10-7. control communications: Inputs, tools & techniques, and outputs

































                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   303
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   324   325   326   327   328   329   330   331   332   333   334