Page 241 - Buried Pipe Design
P. 241

Design of Pressure Pipes  215

































          Figure 4.13 Prequalification flattening test (after flattening).

         pipes. Also note that to reach ten million cycles takes about 1 year
         of continuous operation. The temperature was held at 22    2 C
         (71.6   3.6 F) for all tests.
           Test One was terminated after cycling 10,209,535 cycles with no
         fatigue failures in the PVC pipes. However, during the process of sub-
         jecting these 10 PVC pipe samples to over 10 million cycles, failure of
         six pumps, five relief valves, and some other miscellaneous hardware
         occurred. Test Three and Four were completed prior to Test One
         reaching 10 million cycles. After examining the data  obtained from
         Tests Three and Four, it was determined that 10 million cycles is a con-
         servative estimate of cycles to failure, and failure is more likely to
         occur at around 20 million cycles. Vinson’s equation [Eq. (4.17)] pre-
         dicted this test to fail at 322,000 cycles. This dramatically illustrates
         how Vinson’s method can give very conservative results.
           The number of cycles to failure for tests Two, Three, and Four are
         summarized in Table 4.8. Only two of the five pipes tested in Test Two
         failed. The remaining three pipes survived over 11 million cycles with-
         out failure. Where the number of cycles to failure is high, there
         appears to be a larger scatter in the results. Tests Three and Four have
         very consistent results. In developing fatigue failure criteria, the low-
         est number of cycles to failure for each test condition in Table 4.8 was
   236   237   238   239   240   241   242   243   244   245   246