Page 312 - Failure Analysis Case Studies II
P. 312

297

                                                              Pipe   Polystyrene

                                                  Screed



                                                1        Floor oanel    1



                                              4
                                              I






                                          t-330---
                                            Fig. 14. The corroded steel pipe. Dimensions in mm.



                       were laid in the concrete during the construction. By  1985, the pipes had started to leak. A typical
                       failure is shown in Fig. 14. The pipe had an outside diameter of  x 30 mm, and a wall thickness of
                       x4mm. It had been cast into the floor panel of one of the student rooms, and was insulated with
                       slabs of expanded polystyrene. When the floor was dug up, it was found that the pipe had rusted
                       from the outside. The wall of the pipe had perforated, and the water inside the heating system had
                       started to leak out. The corrosion deposits were reddish-brown in colour.


                       8.2.  Failure analysis
                        The roof of the building consisted of a series of horizontal  pre-cast concrete slabs. These had
                       started to take in rain-water at the joints. The structure of the building was complex, and the rain-
                       water travelled large distances before leaking into the rooms or the public areas. It was concluded
                       that the most likely explanation for the corrosion was that the pipes had come into contact with the
                       leaking rain-water. The horizontal runs of piping on each floor were connected by vertical runs laid
                       in open ducts, and it was thought that these could have channelled the rain-water from one floor to
                       another.
                        Since air was able to get to the surface of the pipe, the cathodic oxygen-reduction reaction would
                       have taken  place  easily. In  addition,  the  incoming rain-water  would  have been  saturated  with
                       oxygen. The corrosion product was presumably red rust (hydrated Fe,03). The Pourbaix diagram
                       for iron (see Appendix A) shows that this oxide is produced when the oxygen content is high. Rain-
                       water is also saturated with carbon dioxide: it contains  % 1300mgI-'  of the gas [3]. The carbon
                       dioxide converts to carbonic acid, and the pH falls to  =4.5 as a result [2]. As can be seen from the
                       Pourbaix diagram, rain-water is aggressive to mild steel: iron cannot start to produce an oxide film
                       at a pH of 4.5 unless the potential is taken up to +0.4V. A strong oxidizing agent would be needed
                       to get the potential this high.
                        Mild  steel  typically  corrodes  at  the  rate  of  0.05-0.15mm/year  in  slowly moving  soft  water
                       saturated with air at  15°C [16]. However, the pipes were not always at 15OC: when the heating
                       system was operating they were closer to 70 "C. Figure 6 shows that the corrosion rate should go
                       up by  ~2.7 times over this temperature interval. The heating system was generally used only for 6
                       months out of each year; on average the corrosion rate was probably  x 1.8 times greater than it
                       would have been at 20 "C. This would give a corrosion rate of  x0.09-0.27 mm/year. If it is assumed
                       that rain-water had been leaking into the building for x 7 years, the depth of attack would be x 0.6-
                       1.9 mm. If the steel develops pitting corrosion, the rate of attack in the pit can be up to 10 times the
                       rate of general corrosion [ 161. In this case, the pits would easily be capable of perforating the wall
   307   308   309   310   311   312   313   314   315   316   317