Page 383 - Hydrocarbon Exploration and Production Second Edition
P. 383

370                                Risk Analysis for Major Capital Investments in Projects


                                     EMV of decisionvs Appraisal cost
                  130
                                                     Appraise    Develop
                  120
                 ($mln)  110

                 Decision  100



                 of  90
                 EMV  80

                   70

                   60
                      0       10       20       30       40       50       60
                                          Appraisal cost ($mln)
          Figure 15.4  Sensitivity analysis to determine the maximum value of appraisal information.





          risk or opportunity is identified, the more potential there is to create value, and
          similarly the later it is identified the more erosion of project value will typically
          occur (Figure 15.5).
             The following table briefly indicates the activities which occur at each stage.


           Stage                                 Activity
           Identify    Identify the opportunity for investment.
           Assess      Consider options for development and demonstrate that at least one is
                         economically feasible. Determine whether further appraisal activity is
                         required to improve the project value.
           Select      Choose between the options generated, based on economic,
                         environmental and safety criteria.
           Define       Perform detailed design of the chosen concept for development.
           Execute     Procure suppliers and agree the contracts for constructing the facilities,
                         processing equipment and drilling. Fabricate, install and commission
                         the plant.
           Operate     Operate the facility.


             The Assess stage can also be called the Appraise stage in some companies, and the
          stage-gate process clearly has its roots in the traditional planning and control
          approach discussed in Section 13.2, Chapter 13.
             There are useful risk analysis tools which can be applied at the above stages, and
          these will now be introduced.
   378   379   380   381   382   383   384   385   386   387   388