Page 519 - Industrial Power Engineering and Applications Handbook
P. 519

Instrument and control transformers: application and selection  151493
          (iii) Power frequency withstand test on the secondary   (c) D.C. discharge test.
              windings. This must  also be conducted only on   (d) Impulse voltage withstand test.
              the electromagnetic unit of a VT, as noted above,   (e) Partial discharge (ionization) test.
              at 2 kV for  1 minute, similar to the control and   2  Temperature rise test.
              auxiliary circuit dielectric test (Table  14.3).   3  Impulse voltage withstand test.
          (iv) Verification of accuracy: as under type tests above.   4  Ferro-resonance test.
          Field tests  Power frequency  withstand test  on the   5  Transient response test.
          primary  windings (for un-grounded VTs). The value   6  Verification  of accuracy.
          of  the test  voltage and the test procedure,  is  almost
          the  same as that for a switchgear assembly (Section   Routine tests
           14.5).
          Additional  tests  on  a  capacitor  VT  The  tests   1  Tests on capacitors
          discussed above refer generally to the electromagnetic   (a)  Capacitance and tangent of the loss angle (tan 6)
          unit  only. To test  the whole VT,  the following tests   (b) Power frequency dry withstand test
          are recommended.  For the test procedure and results   (c) Sealing test
          refer  to IEC 601886.                        2  Verification  of terminal marking
                                                       3  Power frequency withstand test on the secondary circuit
                                                       4  Verification  of accuracy
        Type tests
                                                       15.10.2 Current transformers
        I  Tests on capacitors
          (a) Self-resonating frequency test - applicable only   1  Type tests These will  cover the following tests:
             to carrier coupling capacitors.              (i) Short-time current (Isc) test
          (b) Power frequency  wet  withstand  test  on  outdoor   (ii) Momentary peak or dynamic current test. (This
             capacitors.                                     must be conducted at a minimum of 2.5 /sc)





                    R    YorN
                    T    T
                                        r7

                                        1R'   1Y'or IN'      mr7
                    R'   Y'or  N        r7                   R'   N   R'   N'
                  (1) Single phase VT                      (5) Single phase residual VT
                                        2R'   2Y'or  2N
                                    (2) Single phase VT with two
                                       secondary windings

                                                                                  2"
                                      R   Y   B  N
                                      t   t   t  t
                 i  i  PT                                                   B A



                 '1'1-1               Y  Y   J B'   TN                                  Y
                                      B  B t i





                  (3) 3-phase VT



                                    (4) 3-phase VT with two   (6) 3-phase residual VT   Y"
                                      secondary windings
                       Figure 15.35  Single and three-phase VTs with one and two windings  in the secondary
   514   515   516   517   518   519   520   521   522   523   524