Page 613 - Industrial Power Engineering and Applications Handbook
P. 613

17/578 Industrial Power Engineering and Applications  Handbook

         as a power station or a process plant, to avoid the least   Test results
         risk. In our discussion  so far, the circuit conditions, as
         assumed  and  the  analysis  of  the  voltage  surges  as   The test circuit may be connected to the test voltage and
         generated, were purely statistical and varied from machine   then switched to obtain the required oscillograms during
         to  machine  and from one installation  to  another.  The   switching operations and assess the following:
         purpose so far has been to provide a general analysis of
         surge  voltage  phenomenon,  its  consequences  on  the   Any restrikes and their number
         machine  and possible  remedies  and/or  protection.  For   Amplitude of voltage surge (V,) generated and
         absolute motor protection, accurate transient conditions   Their rise time (t,).
         must  be known. To determine the transient  conditions
         accurately, a working committee of the IEEE-Cigre has   With these data, one can determine the dielectric curve
         suggested a simulated test circuit (Electra,  198  I; Gibbs   the  machine  must  have  when  switched  with  such  an
         et al.,  1989) for all manufacturers of interrupting devices   interrupting device. This can be compared with the actual
         (1)  to  determine  the  behaviour  of  their  devices,  with   dielectric curve of the machine (Figure 17.18) obtained
         predetermined circuit parameters, almost representing a   from its manufacturer to decide the compatibility of the
         normal  supply  side  of  the  machine;  (2) to  assess  the   interrupting device for the machine or vice versa and the
         behaviour  of the machine during a switching operation   extent of surge protection, if necessary. For more details
         and subsequent restrikes,  if  any, as a guideline  for the   and results of similar simulation tests, see Central Board
         user; and (3) to decide on the more appropriate switching   of Irrigation and Power (1 995).
         device for the machine and its surge protection, based on
         the dielectric capability of the machine (Figure 17.18).
         The test circuit is illustrated in Figure 17.19 simulating:   17.1 0  Protection of rotating machines
                                                               from switching surges
           On  the  supply  side of  the  interrupter, an  equivalent
           busbar,  inductance  and  lumped  capacitance  with  a   For adequate protection of the machine it is essential to
           provision  to  connect  p.f.  correction  capacitors,  if   know the amplitude, V,, and the rise time, tl of the severest
           required, to represent a replica of the actual installation.   voltage surge (FOW) that may occur on the system. It is
           On the load side, the interrupter is connected through   recommended that the actual field tests be conducted for
           a  cable  to  the  equivalent  circuit,  with  the  required   large  installations  according  to  the  recommended
           quantities of  lumped  resistance  and  reactance,  to   simulation test circuits, noted above, to ascertain these
           represent the motor to be tested, under a locked rotor   surges.
           condition.  The  circuit  would  also  represent  an   The  tests  may  be  conducted  on  a  few  ratings  with
           interruption immediately after a start, to check for the   different sizes and lengths of cables to simulate the near
           most onerous operating condition  for the  interrupter   actual condition of the installation. One should be more
           to generate the highest surges as discussed earlier.   conservative than liberal on cable lengths to obtain safe



                      I          I           I   1                I
                      '  Supply source  '  Busbar section   Test circuit   Cable   ~   Motor substitute
                                             1   1   breaker                            I
                                             8   ,
                      I          I           I   1                                      I
                                                                                 L    R











                   Typical parameters as recommended by ClGRE
                   2,  = Grounding impedance = 5 Q      L  = Load inductance
                   L,  = Source inductance = 4  mH      R  = Load resistance
                   C,   = Compensation capacitance = 0.0  or 7.0 pF   C,  = Load parallel capacitance
                   C,  = Busbar capacitance = 40 nF     Rp = Load parallel resistance
                   L,  = Busbar inductance = 25 pH
                   Cable = 100 m screened, radial field 3 X
                   Unipolar Z, = 40 a, 95 mmZ AI unrolled and grounded at both ends.
                                         Figure 17.19  A simulated test circuit
   608   609   610   611   612   613   614   615   616   617   618