Page 273 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 273

252 Industrial process plant construction estimating and man-hour analysis



              Example 12.6.2
              Diesel power plant—handle and install pipe, carbon steel, and welded joint
              (Table 12.6.2 and Fig. 12.6.2)
                 Facility—diesel power plant
                 Data for input: man-hour field handle S10S and lighter stainless steel pipe
                 Man-hour (y): R 1 = 0.15, 0.15, 0.18, 0.24, 0.36, 0.48, 0.60, 0.72, 0.84, 0.96,
              1.08, 1.20, and 1.44
                 Pipe size, inches (x): R 2 = 2, 2.5, 3, 4, 6, 8, 10, 12, 14, 16, 18, 20, and 24
                 Man-hour per LF



                         TABLE 12.6.2 Handle pipe—0.375 or less WT
                                                    00
                         X                   Y
                         Pipe
                         size                MH/LF
                         2                   0.15
                         2.5                 0.15
                         3                   0.18
                         4                   0.24
                         6                   0.36
                         8                   0.48
                         10                  0.60
                         12                  0.72
                         14                  0.84
                         16                  0.96
                         18                  1.08
                         20                  1.20
                         24                  1.44




                 COVAR (R 1 , R 2 )       2.91
                 VARP (R 2 )              0.17
                 SLOPE (R 1 , R 2 )       0.0596
                 INTERCEPT (R 1 , R 2 )   0.0067
   268   269   270   271   272   273   274   275   276   277   278