Muchinery Foundations and  Grouting   135

                               OF  THE  BASEPLATE.   IF  MORE  GROUT  IS  NEEDED  THAN  CAN
                               BE  PREPARED  IN ONE  MIXING  BOX,  A  SECOND  BOX  SHALL  BE
                               EMPLOYED.   SUBSEQUENT  BATCHES  OF  GROUT  SHOULD  RE
                               PREPARED  SO  AS  TO  BE  READY  WHEN  THE  PRECEDING  BATCH
                               HAS  BEEN  PLACED.
                          3.   NO  PUSH  RODS  OR  MECHANICAL  VIBRATORS  SHALL  BE  USED  TO
                               PLACE  THE  GROUT  UNDER  THE  BASEPLATE.
                          4,   ONE  (1)  4"  X  4''  X  4"  TEST  CUBE  SHALL  BE  MADE  FROM
                               EACH  UNIT  OF  GROUT  PLACED.   THE  SAMPLE(S)  SHALL  BE
                               TAGGED  WITH  THE  EQUIPMENT  NUMBER  ON  WHICH  THE  BATCH
                               WAS  USED  AND  WHERE  IN THE  FOUNDATION  THE  BATCH  WAS
                               PLACED.
                     IX.  FINISHING
                          1.   WHEN  THE  ENTIRE  FORM  HAS  BEEN  FILLED  WITH  GROUT.
                               EXCESS  MATERIAL  SHALL  BE  REMOVED  AND  THE  EXPOSED
                               SURFACES  TROWELLED SMOOTH.  THE  TROWEL  SHALL  BE
                               WETTED WITH   FRESH  WATER.  CARE  SHALL  BE  TAKEN  TO
                               PREVENT  BLENDING  WATER  INTO  THE  GROUT  SURFACE,
                          2.   FORMS SHALL  BE  LEFT  IN PLACE  UNTIL  THE  GROUT  HAS  SET
                               AND  THEN  REMOVED.
                          3.   IF  WEDGES  WERE  USED  TO  LEVEL  THE  BASEPLATE,  THEY
                               SHALL  BE  REMOVED  WHEN  THE  GROUT  HAS  SET  BUT  NOT
                               CURED.   AFTER  THE  GROUT  HAS  CURED  THE  WEDGE  VOIDS
                               SHALL  BE  FILLED  WITH  ESCOWELD 7501  PUTTY.
                          4.   THE  REMAINING  CEMENT  GROUT  SURFACES  SHALL  BE  TROWELLED
                               SMOOTH  WITH  A  TROWEL  WETTED  WITH  FRESH  WATER.   SHARP
                               GROUT  EDGES  SHALL  BE  STRUCK  TO  GIVE  A  1/4"  CHAMFER.
                          5.   THE  GROUT  SHALL  BE  KEPT  WETTED  WITH  FRESH  WATER  FOR
                               THREE  (3)  DAYS I
                          6.   THE  GROUT  SHALL  CURE  FOR  SEVEN  (7)  DAYS  WITH   THE
                               AMBIENT   TEMPERATURE  NOT  LESS  THAN  50'F  PRIOR   TO
                               MOUNTING  ANY  EQUIPMENT  ON  THE  BASEPLATE.
                          7.   THE  TOP  OF  THE  BASEPLATE  SHALL  BE  SOUNDED  FOR  VOIDS.
                               AFTER  ALL  THE  VOIDS  HAVE  BEEN  DEFINED  AND  THE  GROUT
                               CURED.  THE  BASEPLATE  SHALL  HAVE  TWO  HOLES  DRILLED
                               THROUGH  TO  EACH  VOID  IN OPPOSITE  CORNERS  OF  THE  VOID.
                               ONE  OF  THE  PAIR  OF  HOLES  SHALL  BE  TAPPED  AND  FITTED
                               WITH  A  PRESSURE  GREASE  FITTING.  THE  OTHER  HOLE
                               SHALL  BE  USED  AS  A  VENT  HOLE  FOR  ITS   VOID.   THE  VOID
                               SHALL  BE  FILLED   WITH   UNFILLED   ESCOWELD 7505  EPOXY
                               WITH  HAND  GREASE  GUN.   CARE  MUST  BE  TAKEN  TO  PREVENT
                               LIFTING  THE  BASEPLATE  SHOULD  A  BLOCKAGE  OCCUR  BETWEEN
                               THE  GREASE  FITTING   AND  THE  VENT.   WHEN  THE  VOID   HAS
                               BEEN  FILLED,  THE  GREASE  FjTTiNG  SHALL  BE  REMOVED  AND
                               BOTH  HOLES  DRESSEL!  SMOOTH.
                          8.   ALL  EXPOSED  GROUT  AND  CONCRETE  SURFACES  SHALL  BE
                               SEALED  WITH  ONE  COAT  OF  UNFILLED  ESCOWELD 7505  EPOXY
                               HAND  APPLIED   WITH   A  PAINT   BRUSH.  THE  EPOXY  SEALER
                               SHALL  BE  TINTED  TO  CONTRAST  WITH  THE  CONCRETE  AND
                               GROUT.

                      X.   CLEAN-UP
                          1.   IMMEDIATELY  AFTER  GROUTING  IS COMPLETED  ALL  TOOLS  AND
                               MIXING  EQUIPMENT  SHALL  BE  CLEANED  USING  FRESH  WATER.