Page 155 - Machinery Component Maintenance
P. 155

Appendix  3-D

                                   specifications for EpoKy

                             Grouting of Rotating Equipment











                              THIS   SPECIFICATION  COVERS  EPOXY  GROUTING  OF  MECHANICAL
                              EQUIPMENT  ON  CONCRETE  FOUNDATIONS.
                          I I ,  MATERIALS
                               1.   EPOXY  SHALL  BE  ESCOWELD 7505  TWO  PART  LIQUID  (EPOXY
                                   RESIN  AND  CONVERTER).
                              2.   FILLER   SHALL  BE  ESCOWELD 7530  SAND  AGGREGATE.
                              3.   ALL  MATERIALS  SHALL  BE  STORED  INDOORS  AND  KEPT  DRY,
                                   FREE  OF  MOISTURE  IN  ITS  ORIGINAL  SHIPPING  CONTAINERS.
                              4,   STORAGE  TEMPERATURES  SHALL  BE  MAINTAINED  BETWEEN  40.F
                                   AND  90.F.   GROUTING   MATERIAL  SHALL  BE  KEPT  AT  65'F
                                   MINIMUM  FOR  48  HOURS  PRIOR  TO  MIXING  AND  PLACEMENT.
                         I I I.  PREPARATION  OF  FOUNDATION
                               1.   FOUNDATION  BOLT  THREADS  SHALL  BE  EXAMINED  FOR  STRIPPED
                                   OR  DAMAGED  THREADS.   THESE  THREADS  SHALL  BE  RECHASED
                                   TO  CLEAN  UP  OR  THE  FOUNDATION  BOLT  REPLACED  IF
                                   NECESSARY,  THE  FOUNDATION  BOLTS  AND  THEIR  THREADS
                                   SHALL  BE  PROTECTED  DURING  THE  LEVELING  AND  GROUTING
                                   OPERATIONS.
                              2.   THE  CONCRETE  FOUNDATION  SHALL  BE  DRY  AND  FREE  OF  OIL.
                                   IF OIL  IS PRESENT  IT  SHALL  BE  REMOVED  WITH  SOLVENT
                                   PRIOR  TO  CHIPPING.
                              3.   THE  CONCRETE  SHALL  BE  CHIPPED  TO  EXPOSE  ITS  AGGREGATE
                                   APPROXIMATELY  1/2  INCH  DEEP  SO  AS  TO  REMOVE  ALL
                                   LAITANCE  AND  PROVIDE  A  ROUGH  SURFACE  FOR  BONDING.
                                   LIGHT  HAND  TOOLS  SHALL  BE  USED  IN CHIPPING.
                              4,  AFTER  CHIPPING.  THE  EXPOSED  SURFACES  SHALL  BE  BLOWN
                                   FREE  OF  DUST  USING  OIL  FREE  COMPRESSED  AIR  FROM  AN
                                   APPROVED  SOURCE.