Appendix 3-C
Detailed Checklist for Rotating
Equipment: Baseplate Grouting
DATE/BY
1. BASEPLATE SURFACES FREE OF OIL, SCALE, AND
DIRT.
2. MOISTURE . OF OIL. DUST, AND
CONCRETE CLEAN AND FREE
3. FOUNDATION BOLT SLEEVES PACKED WITH NON-BOND-
ING MATERIAL.
4. FOUNDATION BOLTS WAXED OR COVERED WITH DUCT
SEAL
5. VENT HOLES UNOBSTRUCTED.
6. FORMS TO PROPER HEIGHT.
7. FORMS PROPERLY BRACED.
8. FORMS IN CONTACT WITH GROUT WAXED,
9. GROUTING MATERIALS IN UNOPENED CONTAINERS:
DRY AND STORED AT APPROXIMATELY 80'F.
10. SUFFICIENT QUANTITY OF MATERIAL ON HAND AT
SITE TO COMPLETE WORK.
11. MIXING BOXES AND TOOLS CLEAN.
THE FOLLOU SECTIONS APPLY TO EPOXY GROUTING
12. AMBIENT TEMPERATURE ABOVE 65'F DURING MIXING.
POUR AND CURE.
13. NO PARTIAL UNITS OF EPOXY, CONVERTER OR SAND
AGGREGATE USED.
14. EPOXY AND CONVERTER HAND BLENDED THREE TO
FIVE MINUTES MAXIMUM,