Page 153 - Machinery Component Maintenance
P. 153

Appendix  3-C


                           Detailed Checklist for  Rotating
                           Equipment:  Baseplate Grouting












                                                                            DATE/BY
                         1.   BASEPLATE SURFACES  FREE  OF  OIL,  SCALE,  AND
                             DIRT.
                         2.   MOISTURE .             OF  OIL.  DUST,  AND
                             CONCRETE  CLEAN  AND  FREE
                         3.  FOUNDATION  BOLT  SLEEVES  PACKED  WITH  NON-BOND-
                              ING  MATERIAL.
                         4.   FOUNDATION  BOLTS  WAXED  OR  COVERED  WITH  DUCT
                              SEAL
                         5.   VENT  HOLES  UNOBSTRUCTED.
                         6.   FORMS TO  PROPER  HEIGHT.
                         7.   FORMS  PROPERLY  BRACED.
                         8.  FORMS IN CONTACT  WITH  GROUT  WAXED,
                         9.  GROUTING   MATERIALS  IN UNOPENED  CONTAINERS:
                             DRY  AND  STORED  AT  APPROXIMATELY  80'F.
                        10.   SUFFICIENT  QUANTITY  OF  MATERIAL  ON  HAND  AT
                              SITE  TO  COMPLETE  WORK.
                        11.   MIXING  BOXES  AND  TOOLS  CLEAN.
                         THE FOLLOU SECTIONS APPLY  TO EPOXY  GROUTING
                        12.   AMBIENT   TEMPERATURE  ABOVE  65'F  DURING  MIXING.
                             POUR  AND  CURE.
                        13.   NO  PARTIAL  UNITS  OF  EPOXY,  CONVERTER  OR  SAND
                             AGGREGATE  USED.
                        14.   EPOXY  AND  CONVERTER  HAND  BLENDED  THREE  TO
                             FIVE  MINUTES  MAXIMUM,