Machinery Foundations and  Grouting   139

                         5.   AFTER  THE  FOUNDATION  HAS  BEEN  CHIPPED  AND  CLEANED,
                              IT SHALL  BE  COVERED  SO  AS  TO  PREVENT  IT FROM
                              BECOMING  WET.
                         6.   FOUNDATION  BOLTS  SHALL  BE  WAXED  OR  COVERED  WITH  DUCT
                              SEAL  OVER  THEIR  ENTIRE  EXPOSED  LENGTH.   IF  THE  BOLTS
                              ARE  SLEEVED,  THE  SLEEVES  SHALL  BE  PACKED  WITH  NON-
                              BONDING  MATERIAL  TO  PREVENT  THE  ANNULAR  SPACE  AROUND
                              THE  BOLT  FROM  BEING  FILLED  WITH  GROUT.

                     IV.  PREPARATION  OF  BASEPLATE
                         1.   SURFACES OF  THE  BASEPLATE  WHICH  WILL  COME  IN  CONTACT
                              WITH  THE  EPOXY  GROUT  SHALL  BE  CLEAN  AND  FREE  OF  ALL
                              OIL.   RUST.  SCALE.  PAINT   AND  DIRT.   THIS   CLEANING   SHALL
                              BE  DONE  IMMEDIATELY  PRIOR  TO  THE  LEVELING  OF  THE  BASE-
                              PLATE  AND  PLACEMENT  OF  THE  EPOXY  GROUT.
                         2.   IF  THE  GROUTING  IS TO  BE  DELAYED  BY  MORE  THAN  EIGHT
                              (8) HOURS  AFTER  THE  BASEPLATE  IS CLEANED,  THE  CLEANED
                              BASEPLATE  SHALL  BE  PAINTED  WITH  ONE  COAT  OF  UNFILLED
                              ESCOWELD 7505  TO  GIVE  A  DRY  FILM THICKNESS  OF  THREE
                              (3)  MILS.  THIS   COAT  SHALL  BE  FULLY  DRIED  PRIOR  TO
                              PLACEMENT  OF  GROUT.
                         3.   IF  THE  EPOXY  COATED  BASEPLATE  IS  NOT  GROUTED  WITHIN
                              THIRTY  (30) DAYS  AFTER  BEING  PAINTED,  THE  EPOXYED
                              SURFACE  SHALL  BE  ROUGHED  UP  WITH  A  WIRE  BRUSH  TO
                              REMOVE  THE  BLOOM  OR  SHINE.   ALL  DUST  PRODUCED  BY
                              BRUSHING  SHALL  BE  WIPED  OFF  USING  A  WATER  DAMPENED
                              RAG.   THESE  SURFACES  SHALL  BE  AIR  DRIED  PRIOR  TO
                              PLACEMENT  OF  GROUT.
                     V.   FORMING
                         1.   ALL  FORMING  MATERIAL  COMING  INTO  CONTACT  WITH  THE
                              GROUT  SHALL  BE  COATED  WITH   COLORED  PASTE  WAX.  THE
                              COLORING  TO  CONTRPST  WITH  THE  FORMING  MATERIALS
                              COLORS  I
                         2.   FORMS SHALL  BE  MADE  LIQUID TIGHT  TO  PREVENT  LEAKING
                              OF  GROUT  MATERIAL.   CRACKS  AND  OPENINGS  SHALL  BE
                              SEALED  OFF  WITH  RAGS,  COTTON  BATTING,  FOAM  RUBBER  OR
                              CAULKING  COMPOUND.
                         3.   CARE  SHOULD  BE  TAKEN  TO  PREVENT  ANY  WAX  FROM  CONTACT-
                              ING  THE  CONCRETE  FOUNDATION  OR  THE  BASEPLATE.
                         4.   ANY  LEVELING  WEDGES  THAT  ARE  TO  BE  REMOVED  AFTER  THE
                              GROUT  HAS  CURED  SHALL  BE  COATED  WITH  WAX.   WEDGES
                              AND/OR  SHIMS  WHICH  ARE  TO  REMAIN  EMBEDDED  IN THE
                              GROUT  SHALL  NOT  BE  COATED.
                         5.   LEVELING  SCREWS,   IF USED.  SHALL  BE  COATED  WITH  WAX.
                     VI.   MIXING
                         1.   AS  EPOXY  COMPOUNDS  HAVE  LIMITED  POT  LIFE  AFTER  MIX-
                              ING,  BOTH  THE  ELAPSED  TIME  FROM  BEGINNING  OF  MIXING
                              TO  THE  COMPLETION  OF  THE  POUR  AND  THE  AMBIENT  TEMP-
                              ERATURES  AT  THE  BEGINNING  OF  MIXING  AND  AT  THE
                              COMPLETION  OF  POUR  SHALL  BE  RECORDED  AND  GIVEN  TO  THE
                              TURBOMACHINERY  ENGINEER  WHO  WILL  RECORD  THE  DATA  IN
                              THE  PERMANENT  EQUIPMENT  RECORDS.