Page 304 - Pipeline Risk Management Manual Ideas, Techniques, and Resources
P. 304

Modeling ideas Ill 131281
               [SCADA System/-   Evaluation of a centralized SCADA sys-   10.0 pts [No Procedures Program]-No  known program exists
               tem for all facilities, including RTU, PLC, PLCC-based appli-   and few company and industry minimum recommended or
               cation  programs,  conditions  monitoring,  remote  control   required procedure best practices are met
               capabilities, automatic alarmdshutdown capabilities, protocols   5.0 pts [Unknown Procedures Program]
               and communication systems.
                                                          [Personnel Qualifications Program]-  Evaluation of the types
               0.0 pts [Not Applicable]                   of training  and  testing  methods,  overall  effectiveness.  ade-
                1 .0 pts  [Excellent  SCADA  System]-A   comprehensive   quacy, and appropriateness of operations, maintenance, engi-
                 SCADA system exists that exceeds all company and industry   neering,  construction,  testing  and  management  personnel’s
                 minimum recommended or required system monitoring and   qualification for performing position requirements.
                 control practices
               3.0 pts  [Adequate SCADA System]-A   semiformal  SCADA   0.0 pts [Not Applicable]
                 system exists that meets all company and industry minimum   1  .O pts  [Excellent  Qualifications  Program]-A   formal  pro-
                 recommended  or  required  system  monitoring  and  control   gram exists that exceeds all company and industry minimum
                 practices                                  recommended or required personnel qualification best prac-
               8.0 pts  [Inadequate SCADA System]-An   informal SCADA   tices
                 system exists that does not meet all company and industry   3 .O pts  [Adequate  Qualifications  Program]-A   semiformal
                 minimum recommended or required system monitoring and   program exists that meets all company and industry mini-
                 control practices                          mum recommended or required personnel qualification best
               10.0 pts  [No  SCADA System]-No   known  SCADA system   practices
                 exists  and  few  company  and  industry  minimum  recom-   8.0 pts  [Inadequate  Qualifications  Program]-An   informal
                 mended or required system monitoring and control practices   program exists that does not meet all company and industry
                 are met                                    minimum recommended or required personnel qualification
               5.0 pts [Unknown SCADA System]               best practices
                                                          10.0 pts  mo Qualifications  Program]-No   known  program
               [Documentation  Program/-  Evaluation of various forms of   exists and few company and industry minimum recommended
               documenting current facility conditions and activities, includ-   or required personnel qualification best practices are met
               ing maps, drawings, records, electronic data, etc.   5.0 pts [Unknown Qualifications Program]
               0.0 pts [Not Applicable]                   [Position Anut’ysis/-  Evaluation of the analysis that went into
               1 .O pts  [Excellent  Documentation  Program]-A   formal pro-   defining position responsibilities, tasks, authority, communi-
                 gram exists that exceeds all company and industry minimum   cations, training and testing levels, safety, etc. Includes mainte-
                 recommended or required documentation practices   nance,  engineering,  construction,  testing,  and  management
               3.0 pts  [Adequate  Documentation  Program]-A   semiformal   positions.
                 program exists that meets all company and industry  mini-
                 mum recommended or required documentation practices   0.0 pts [Not Applicable]
               8.0 pts  [Inadequate  Documentation  Program]-An   informal   I .O  pts [Excellent Position Analysis]-A  formal analysis exists
                 program exists that does not meet all company and industry   that  exceeds  all  company  and  industry  minimum  recom-
                 minimum  recommended  or required  documentation  prac-   mended or required position analysis best practices.
                 tices                                    3.0 pts [Adequate Position Analysis]-A   semiformal analysis
               10.0 pts  [No Documentation  Program]-No   known program   exists that meets all company and industry minimum recom-
                 exists  and  few  company  and  industry  minimum  recom-   mended or required position analysis best practices
                 mended or required documentation practices are met   8.0 pts  [Inadequate  Position Analysis]-A   informal  analysis
               5.0 pts [Unknown Documentation Program]      exists that does not meet all company and industry minimum
                                                            recommended or required position analysis best practices
               [Procedures Progrum]-  Evaluation of the types, overall con-   10.0 pts Do Position Analysis]-No  known analysis exists and
               dition,  adequacy, and  appropriateness  of various  operations,   few  company  and  industry  minimum  recommended  or
               maintenance, engineering,  construction, testing and manage-   required position analysis best practices are met.
               ment procedures.                           5.0 pts [Unknown Position Analysis]

               0.0 pts [Not Applicable]                   [Hazard Analyses]-  Evaluation of the historical hazard analy-
               I .O pts  [Excellent Procedures  Program]-A   formal  program   ses conducted for station facilities, including HAZOP, “what-if”
                 exists that exceeds all company and industry minimum rec-   scenarios, fault trees, and relative risk assessment, as part of fail-
                 ommended or required procedure best practices   ure investigations or an overall company risk management pro-
               3.0 pts [Adequate Procedures Program]-A   semiformal pro-   gram.  Analyses  should  be  appropriate,  comprehensive, and
                 gram exists that meets all company and industry minimum   recent, with follow-up ofrisk reduction recommendations.
                 recommended or required procedure best practices
               8.0 pts [Inadequate Procedures  Program]-An   informal pro-   0.0 pts [Not Applicable]
                 gram  exists that does not meet  all  company and  industry   1 .O  pts  [Excellent Hazard Analyses]-Formal   analyses exists
                 minimum recommended  or  required procedure  best prac-   that  exceed  all  company  and  industry  minimum  recom-
                 tices                                      mended or required hazard analysis best practices