13/280 Stations and Surface Facilities
              evaluate the conditions and remotely initiate a full, or partial,   Human error algorithm variables
              shutdown of affected station equipment
            6.0 pts [Remote Monitoring Only]-Condition-sensing  device   [Housekeepin&   Evaluation of facility equipmenUmaterials
              or permissive  limit  exceedences  alarm  at  a  continuously   organization and overall maintenance.
              manned location and requires operators to evaluate the con-
              ditions and on-site manually initiate a full, or partial, shut-   0.0 pts [Not Applicable]
              down of affected station equipment       1 .O pts [Excellent Housekeeping]-All  equipment and materi-
            8.0 pts  [Local Alarms  Onlyl-Condition-sensing  device  or   als  are  well  marked,  accessible,  maintained,  and  exceed
              permissive  limit  exceedences  alarm  at a noncontinuously   industry and company best practices
              manned  location  and  requires  operators  to  evaluate  the   3.0 pts [Adequate Housekeeping]-All  equipment and materi-
              conditions  and on-site  manually  initiate  a  full,  or  partial,   als are marked, accessible, and maintained per industry and
              shutdown of affected station equipment     company best practices
            10.0 pts  [No  Safety  Systems]-No   safety  systems present,   10.0 pts [Inadequate Housekeeping]-Equipment  and materi-
              including condition sensing, permissives, alarms, or  other   als are not well marked,  accessible, andor maintained per
              devices                                    industry and company best practices
            5.0 pts [Unknown Safety Systems]           5.0 pts [Unknown Housekeeping]
            [Safety Systems Adequacy Review Program]-  Evaluation of   [Anti-Freeze Program]-  Evaluation of antifreeze program for
            the adequacy of various station safety systems, including asso-   all facilities, including water drains, control valves, instrumen-
            ciated sensing, measurement, and control devices   tation.
            0.0 pts mot Applicable]                    0.0 pts [Not Applicable]
             1 .0 pts [Excellent Adequacy Review Program]-A  formal pro-   1 .0 pts [Excellent Anti-Freeze Program]-A   formal program
              gram exists that exceeds all company and industry minimum   exists that exceeds all company and industry minimum rec-
              recommended  or required safety system design and “ade-   ommended or required antifreeze practices
              quacy for service” review practices      3.0 pts [Adequate Anti-Freeze Program]-A  semiformal pro-
            4.0 pts [Adequate Adequacy Review Program]-A  semiformal   gram exists that meets all company and industry minimum
              program  exists that meets all company and industry mini-   recommended or required antifreeze practices
              mum recommended  or  required  safety system design  and   8.0 pts  [Inadequate  Anti-Freeze  Program]-An   informal
              “adequacy for service” review practices    program  exists  that  does  not  meet  all  company  and
             8.0 pts [Inadequate Adequacy Review Program]-An  informal   industry  minimum  recommended  or  required  antifreeze
              program exists that does not meet all company and industry   practices
              minimum recommended  or required safety system design   10.0 pts mo Anti-Freeze Program]-No  known program exists
              and “adequacy for service” review practices   and few company and industry minimum recommended or
             10.0 pts Po Adequacy Review Program]-No  known program   required antifreeze practices are met
              exists  and  few  company  and  industry  minimum  recom-   5.0 pts [Unknown Anti-Freeze Program]
              mended or required safety system design and “adequacy for
              service” review practices are met         [Computer Permissives Program]-  Evaluation of a computer
             5.0 pts [Unknown Adequacy Review]         permissives program for all facilities, including PLC, PLCC,
                                                        SCADA,  and  other  logic-based  application  programs.
             (Safety S’stems  PPM]-  Evaluation of various station safety   Permissive  programs  that  control  safe  operations  of  valve
             system’s “predictive  and  preventative  maintenance”  (PPM)   alignments, pressures, flows, and temperatures are considered.
             programs, including equipmentkomponent inspections, moni-
             toring,  cleaning,  testing,  calibration,  measurements,  repair,   0.0 pts mot Applicable]
             modifications and replacements.            1 .O pts  [Excellent  Permissives Program]-A   comprehensive
                                                         computer-based  program  exists that  exceeds  all  company
             0.0 pts [Not Applicable]                    and industry minimum recommended or required permissive
             1.0 pts [Excellent PPM Program-A  formal program  exists   practices
              which exceeds all company and industry minimum recom-   3.0 pts [Adequate Permissives Program]-A  semiformal com-
              mended or required PPM practices.          puter-based  program  exists  that  meets  all  company  and
             4.0 pts  [Adequate PPM Program-A   semi-formal  program   industry  minimum  recommended  or  required  permissive
              exists which meets all company and industry minimum rec-   practices
              ommended or required PPM practices.       8.0 pts [Inadequate Permissives Program]-An  informal com-
             8.0 pts  [Inadequate  PPM  Program]-An   informal  program   puter-based program exists that does not meet all company
              exists which does not meet all company and industry mini-   and industry minimum recommended or required permissive
              mum recommended or required PPM practices.   practices
             10.0 pts  Po PPM Program]-No   known program exists and   10.0 pts  [No  Permissives  Program]-No   known  computer-
              few  company  and  industry  minimum  recommended  or   based program exists and few company and industry mini-
              required PPM practices are met.            mum recommended or required permissive practices are met
             5.0 pts [Unknown PPM Program]              5.0 pts [Unknown Permissives Program]