Page 78 - Pipeline Risk Management Manual Ideas, Techniques, and Resources
P. 78

Third-party damage mitigation analysis 3/57
               Table 3.3  Patrol as an opportunity to prevent failures caused by   Mitigation effectiveness for third-party damage-
               third-party damages Spectrum of  third-party activities used to   A scenario-based evaluation
               produce “probability of detection” graph (Figure 3.9)
                                                          Hypothesis to be examined
                                 Activity duration
                                 (includes evidence         At least 9 out of 10 third-party damage failures that would be other-
                                   remaining)              wise expected are avoided through the stringent implementation of
                                                           the proposed mitigation plan.
                                     Frequencvof   Cumulative
               4ctiviry        Davs   occurrence   frequency   Discussion
               Highway construction   14   0.03   0.03     This failure estimation is suggested by modeling and analyses shown
               Subdivision work   13   0.03      0.06      elsewhere in this environmental assessment, There is a question of
                                12     0.03      0.09      whether such an estimation can be supported by a logical event-tree
                                It     0.03      0.12      type analysis and examination of some ofthe past failures. Therefore,
                                10     0.05      0.17      the  objective is  to determine if  the proposed  mitigation measures
                                9      0.05      0.22      could have interrupted past failure sequences, at least 90 percent of
               Buried utility crossings   8   0.07   0.29   the time, under some set ofreasonable assumptions.
                                7      0.07      0.36
                                6      0.07      0.43       Third-party damage (or “outside force”) is a good candidate
               Drainage work     5     0.1       OS3      for this examination since this failure category is often viewed
               Swimming  pools   4     0.1       0.63     as the most random and hence, the least controllable through
               Land clearing    3      0.1       0.73     mitigations. Seven (7) out oftwenty-six (26) historical leaks on
               Agricultural work   2   0.1       0.83     the subject pipeline were categorized as being caused by “third-
               Seismograph crew   1    0.1       0.93     party damage.” It is useful to characterize these incidents based
               Fence post installation   0.5   0.05   0.98
               Other            0. I   0.01      0.99     on  some situation specifics. At  least six (6) of the incidents
                                                          involved heavy equipment such as back hoe, bulldozer. bull-
               Source  URS  Radian  Corporation, ‘“Environmental Assessment  of   dozer with ripperiplow, and ditching machine (the seventh is
               Longhorn Partners Pipeline.” report prepared for US  EPA and DOT,   not listed). Five (5) of the incidents suggest that a professional
               September 2000                             contractor was probably involved since activities are described
                                                          as cable installations, water line installations, excavations for
               Less than once per month           2 pts   an oil/gas company, land clearing, etc. At least four (4) of these
               Never                              0 pts   events occurred  before  a  One-Call  system  was  available in
                                                          Texas (beginning in the early 1990s and mandated in late 1997).
                 Select the point value corresponding to the actual patrol fre-   So, the opportunities for advance knowledge of the presence of
               quency. This schedule is built for a corridor that has a frequency   the pipeline was limited to signs, ROW indications, and per-
               of  third-party  intrusions  that  calls  for  a nominal  patrol  fre-   haps some records ifthe excavator was exceptionally diligent in
               quency of 3 days per week. In this case, the evaluator feels that   a pre-job investigation. Contractor and public education efforts,
               daily patrols  are perhaps justified and provide a measurably   ROW condition, and actual patrol frequency are unknown. Based
               greater safety margin. Frequencies greater than once per day   on current  survey information,  depth of  cover at  these  sites
               (once per  8-hour shift, for instance) warrant no  more points   varies from 19 inches to over 48 inches.
               than daily in this example.                  Scenarios have been  created to address the question: “How
                 The evaluator may wish to give point credits for patrols dnr-   many  failures,  similar  to  these  past  incidents, might  occur
               ing activities  such  as close  interval  surveys (see  Chapter 4,   today?” These scenarios take into account the proposed mitiga-
               Corrosion Index). Routine drive-bys, however, would need to   tion measures. Two tables are offered to show potential failure
               be carefully evaluated for their effectiveness before  credit  is   sequences and opportunities to interrupt those sequences. Since
               awarded.                                   the previously discussed incidents occurred despite some preven-
                 An example of an analysis of “opportunity to detect” poten-   tion measures, the estimates are showing opportunities for dam-
               tially damaging third-party actikities is shown in the example   age avoidance above and beyond prevention practices thought to
               below.                                     be prevalent at the time of the incidents. These tables are loosely
                                                          using terminology to represent frequency of events and probabil-
                                                          ity of events-this  is not a rigorous statistical analysis.
               Third-party damage mitigation analysis       In the first table, the estimated probabilities of various sce-
                                                          nario elements are presented. The table begins with the assump-
               A type of scenario risk analysis of third-party damage prevention   tion that a potentially damaging third-party activity is already
               effectiveness was done as part of an environmental assessment   present in the immediate vicinity ofthe pipeline.
               for a proposed pipeline [86]. This analysis is mostly an exercise   Given that an activity is present, column 2 of the table char-
               in logic, testing whether it is plausible that mitigation measures   acterizes the distribution of likely activities. The distribution
               could markedly reduce third-party damage failures from previ-   assumes a predominance of heavy equipment involvement in
               ous levels. This analysis is interesting not only because it demon-   previous incidents, and is therefore conservative since that cat-
               strates a type  of analysis, but  also because it discusses many   egory is perhaps the most threatening to the pipeline.
               concepts that underlie our beliefs about third-party failure poten-   Column 3 examines the possibility, under today’s mandated
               tial. Excerpts from the analysis ofRef. [86] follow.   and advertised One-Call system. that the system is used and the
   73   74   75   76   77   78   79   80   81   82   83