Page 289 - Sustainability in the Process Industry Integration and Optimization
P. 289

266   C h apter  Ele v e n


                               Analysis=Single Component Reference Contm No. 1 [COD]
                                           Limiting Composite Curves
                          30.0

                          25.0

                        Concentration [ppb]  20.0


                          15.0

                          10.0

                           5.0


                            0.0         0.2        0.4         0.6         0.8
                                                 Mass [t/h]
                                   Limiting CC                Water Supply Line
                     FIGURE 11.8  Limiting Composite Curve generated by WATER software.



                        Four different design options were generated that considered
                     both the maximum reuse analysis and regeneration reuse analysis
                     (Figure 11.9). Design options A and B were based on the maximum
                     reuse analysis, and both achieve a freshwater consumption of 188 t/h;
                     this is a reduction of about 22 percent from the actual freshwater
                     consumption of 240 t/h. Because of process limitations and
                     restrictions, there was no further scope for water reuse. Yet results
                     from the diagnostic stage indicated that a 31 percent reduction in
                     freshwater and wastewater was possible. This additional extent is
                     achievable by regenerating wastewater and then reusing it in other
                     operations. Design options C and D are based on the regeneration
                     reuse analysis; both result in total freshwater consumption of 169
                     t/h, which amounts to a 30 percent reduction—that is, nearly all of
                     the theoretical maximum predicted by Eq. (11.2), the expression for
                     MTFWR.
                        The reduction in freshwater use was achieved by rerouting water
                     streams, a modification that requires new pipes. Design option A
                     requires five new pipes; this is fewer than options B or D, which
                     require seven pipes, and option C, which requires nine new pipes.
                     New piping will affect investment cost. The five new pipes identified
                     for design option A are also required in the other options for the
                     same function and at similar flow rates. Therefore, this option
                     requires the least investment and option C the most. Furthermore,
                     design options C and D each require additional investment cost for a
   284   285   286   287   288   289   290   291   292   293   294