Page 372 - The Tribology Handbook
P. 372

c19              Commissioning lubrication systems



               Running tests and adjustments
               SYSTEM  OPERATION                                 CONTROLS
                 Operate system until lubricant is seen to be discharging   Where  adjustable  electrical  controls  are incorporated,
               at all bearings. If systems incorporate metering valves, each   e.g.  timeclock, these should be set as specified.
               valve should be individually inspected for correct operation.
                                                                 ALARM
               ADJUSTMENT                                          Electrical  or  mechanical  alarms  should  be  tested  by
                 In the case of direct-feed systems, adjust as necessary the   simulating system faults and checking that the appropriate
               discharge(s)  from the  pump  and, in  the  case of  systems   alarm functions. Set alarms as specified.
               operating from a pressure line, adjust  the discharge from
               the metering valves.
                                                                 Fault finding
               RELIEF  OR BYPASS  VALVE
                 Check that relief or bypass valve holds at normal system-   Action recommended in the event of trouble is best deter-
               operating pressure and  that  it will  open at  the specified   mined  by  reference  to  a simple  fault  finding  chart  as
               relief pressure.                                  illustrated in Table  19.2.


               CIRCULATION  SYSTEMS

                               --
               Corn miss ion i ng procedure                                                           TO
                                                                                             1
                                                                                                      :!INTS
                1  Flush  system.  Note:  circulation  systems  must  be          R~~uR*    -/
                                                                                                      APPLICATION
                  thoroughly flushed through to remove foreign solids.   Ir-‘
               2  Check main items of equipment.                  TANK(S1
                                                                                  ..--111111
               3  Test-run and adjust.                                   PUMP(S)   INTERMEDIATE  EQUIPMENT
                 No special equipment is required to carry out the above
               but  spare pressure gauges  for  checking system pressures,   Figure  19.2 Schematic  diagram  of  typical  oil-
               etc.,  and flexible hoses for bypassing items of equipment,   circulation system. Oil is discharged to points of appli-
               should be available.                              cation, returned and re-circulated

               Flushing

                1  Use the same type of oil as for the final fill or flushing   4  During flushing, tap pipes and flanges and alternate oil
                  oil as recommended by  the lubricant  supplier.   on an eight-hour heating and cooling cycle.
               2  Before commencing flushing, bypass or isolate bearings   5  After flushing drain oil, clean reservoir, filters, etc.
                  or  equipment  which  could  be  damaged  by  loosened   6  Re-connect bearings and equipment previously isolated
                  abrasive matter.                                  and refill system with running charge of oil.
               3   Heat oil to 60-70°C  and continue to circulate until the
                  minimum  specified  design  pressure  drop  across  the
                  filter is achieved over an eight-hour period.


               Main items of equipment

               RESERVOIR                                         MOTOR-DRIVEN  PUMP(S)
                (a)  Check reservoir is at least two-thirds full.   (a)  Where fitted, check coupling alignment.
                (b)  Check oil is the type and grade specified.   (b)  Check for correct current characteristics.
                (c)  Where heating is incorporated,  set temperature-regu-   (c)  Check electrical circuits.
                   lating instruments as specified and bring heating into   (d) Check for correct direction of rotation.
                   operation at least four hours prior  to commencement   PUMP RELIEF  VALVE
                   of commissioning.
                                                                   Note setting of pump relief valve, then release spring to
                                                                 its fullest extent, run pump motor in short bursts and check
                ISOLATING AND  CONTROL  VALVES                   system for leaks.
                   Where fitted, the following valves must initially be left   Reset relief valve to original position.
                   open: main suction; pump(s) isolation; filter isolation;
                   cooler isolation  ; pressure-regulator bypass.   CENTRIFUGE
                   Where  fitted,  the  following valves  must  initially  be   Where a centrifuge is incoporated in the system, this is
                   closed :  low  suction;  filter  bypass;  cooler  bypass ;   normally  commissioned  by  the  manufacturer’s  engineer,
                   pressure-regulator isolation ; pressure-vessel isolation.   but it should be checked that it is set for ‘clarification’ or
                   For initial test ofitems of equipment, isolate as required.   ‘purification’ as specified.

                                                           c19.2
   367   368   369   370   371   372   373   374   375   376   377