Meetings and Communications  251
                                                                                   Exhibit 13-5
                                              Party
           Agenda Item                        Responsible  Due Date  Comments      Sample agenda
                                                                                   for a project
            1. Names of participants
                                                                                   meeting.
            2. Review status of the
              construction documents
            3. Review procurement of long lead items
            4. Review bid and award status
            5. Review construction status
            6. Review project schedule
            7. Review project budget
            8. Review status of open change orders
            9. Review status of outstanding
              requisitions
           10. Review project status reports
           11. Review status of progress payments
           12. Review filings and permits
           13. Review insurance program
           14. Review shop drawing status
           15. Review open Requests for
              Information (RFI)
           16. Review open Field Information
              Memos (FIM)
           17. Review status of controlled inspections
           18. Review status of QC program
              and punch list
           19. Review project incident and safety
              reports
           20. Update open items list
           21. Review any new business




          Schedule Meeting

          Schedule meetings should parallel the timing and process of the budget meetings. All
          items that are budgeted must be scheduled and vice versa. The schedule should iden-
          tify all major project milestones, preconstruction period, bid and award period, con-
          struction period, project phasing requirements, project close-out, and owner’s items
          such as furniture deliveries and move-in. Exhibit 13-7 is a sample agenda of a schedule
          meeting.


          Bid and Award Meeting
          These meetings are held with each of the major subcontractors or contractors who are bid-
          ding on the project. Once the bids are opened and leveled, the three responsive bidders (not
          necessarily the lowest bidders) are called in to review their bids, the scope of the work,