Page 299 - Urban Construction Project Management
P. 299

254    Chapter Thirteen
         Exhibit 13-7
                                                                Party
         Sample agenda        Agenda Item                       Responsible  Due Date  Comments
         for a schedule
                               1. Names of participants.
         meeting.
                               2. Review status of the
                                 project schedules.
                                   Pre-construction schedule.
                                   Bid and award schedule.
                                   Construction schedule.
                                   Project close-out schedule.
                               3. Identify any items of work
                                 not on the schedule.
                               4. Identify the critical path
                                 of the schedule.
                               5. Identify and track long lead items,
                                 along with their procurement,
                                 manufacturing, and delivery.
                               6. Identify corrective action plans if
                                 the schedule is not being adhered to.
                               7. Identify all activities for the project,
                                 including work performed by the
                                 consultants (delivery of project
                                 documentation), by the owner
                                 (delivery of the owner’s directly
                                 purchased materials, i.e., furniture
                                 systems, carpet, accessories,
                                 security, A/V systems, and
                                 telecommunications systems),
                                 and by other parties working
                                 at the site (other base building
                                 CM/GC, other tenant CM/GC,
                                 and specialty contractors) and
                                 incorporate them into the
                                 overall project schedule.
                               8. Identify milestones in the schedule
                                 that need to be met in order for the
                                 project to be on schedule
                                 (approvals, permanent power,
                                 enclosure, roof, elevators, controlled
                                 environment for finishes, hoist
                                 removal, derrick and crane removals).
                               9. Identify the target date for obtaining a
                                 temporary/final certificate of occupancy.
                              10. Review resource loading of schedule.
                              11. Review cost loading of schedule.
                              12. Review any open scheduling items.
                              13. Review any new business.