252    Chapter Thirteen
         Exhibit 13-6
                                                              Responsible
         Sample agenda        Item                            Party        Due Date    Comments
         for a budget
                               1. Names of participants.
         meeting.
                               2. Review owner’s program.
                               3. Review status of the design
                                 documents.
                               4. Determine best approach to
                                 budget the project as the
                                 design and construction
                                 documents develop.
                               5. Review latest trade budget
                                 developed by CM/GC
                                 a. By trade
                                 b. By breakdown of work
                                   within each trade
                                 c. Review allowances within
                                   each trade
                               6. Identify items requiring
                                 clarification and further
                                 breakdowns.
                               7. Identify items that have a
                                 budget allowance and
                                 review program and design.
                               8. Define the general conditions
                                 and review the budget for same.
                               9. Define the CM/GC fee and review
                                 budget for same.
                              10. Define insurance requirements
                                 and review budget for same.
                              11. Define bonding requirements
                                 and review budget for same.
                              12. Identify what overtime may be
                                 required for the project and
                                 budget same, either in each
                                 individual trade line item, or as
                                 a separate overtime line item
                                 for each trade.
                              13. Identify costs for project logistics,
                                 such as cranes, derricks, hoists,
                                 scaffolding, and sidewalk bridges.
                                 Establish appropriate line items
                                 within the budget or within each
                                 trade for same, depending on who
                                 will be providing them.
                              14. Establish a design contingency
                                 for the owner and the
                                 consultants to use for design
                                 changes.