Meetings and Communications  255
                                                                                   Exhibit 13-8
                                             Responsible
           Agenda Item                       Party        Due Date   Comments      Sample agenda
                                                                                   for a bid and
            1. Names of participants.
                                                                                   award meeting.
            2. Determine the pre-qualification
              process for subcontractors bidding
              the project.
            3. Review the subcontractors’ bidders
              list and finalize it.
            4. Develop a sample bid package for
              all parties to review.
            5. Develop a bid response form.
            6. Determine who will receive the bids
              and how, where, and by whom will
              they be received and opened.
            7. Determine the role of the owners
              or outside consulting auditing
              firms in the bid and award
              process, and plan accordingly.
            8. Develop a list of alternative prices
              to be included in the bid.
            9. Develop a list of unit prices to be
              included in the bid.
           10. Develop a bid leveling sheet to
              document the receipt of the bids.
           11. Identify the long lead items,
              and bid them to equipment
              manufacturers directly to ensure
              that they are available at the
              project site in accordance with
              the project schedule.
           12. Prioritize the sequence in which the
              construction subcontractor trades
              will be bid, as they cannot all be bid on
              at once by the CM/GC project team.
              Develop a specific bid and award
              schedule for each trade.
           13. Review the bid leveling process
              to determine the responsive
              subcontractor.
           14. Analyze any exclusions and
              qualifications that the subcontractor’s
              bid may contain to eliminate them, and
              ensure an award for a complete scope
              of work.
                                                                      (Continued)