Page 298 - Urban Construction Project Management
P. 298

Meetings and Communications  253
                                                                                   Exhibit 13-6
                                           Responsible
           Item                            Party         Due Date   Comments       (Continued)
           15. Establish the construction
              contingency, separate from
              the design contingency, to
              cover items encountered
              during the construction process.
           16. Establish the formulation for
              a guaranteed maximum price
              (GMP), if one is contractually
              required.
           17. Update budget open items list.
           18. Anticipated cost review.
           19. Review budget qualifications
              and exclusions.
           20. Evaluate value engineering
              options if the project is over
              budget.
           21. Evaluate special administrative
              programs and the cost to
              administer and comply with same.
           22. Review any new business.





          project requirements, schedule, insurance, phasing, and out of sequence work to ensure that
          the bid is complete and to make adjustments as required to properly level the bids and com-
          plete the analysis of the same. Subcontractors are often asked to sign the leveling sheet to
          ensure that they have the full scope of work and to avoid future misunderstandings there-
          after. Chapter 16 explains the bid leveling process and contains examples of bid leveling
          sheets. A sample agenda for a bid and award meeting appears in Exhibit 13-8.

          Coordination Meeting

          Coordination meetings are held by the CM/GC with all of the pertinent subcontractors
          to coordinate the timing, location, and sequence of work to be installed for the project.
          The sheet metal/mechanical subcontractor usually starts the coordination process, given
          that the ductwork and piping is large and is the least flexible component to be installed.
          Once the sheet metal and piping right of ways have been established, the other trades
          such as the plumber, electrician, and sprinkler subcontractors will place their work on
          the coordination drawing and identify any conflicts that may exist. It is important that
          no construction materials be installed prior to the processing and approval of the coor-
          dination by all of the trades. If a subcontractor installs construction materials prior to
          the approval of the coordination drawing, then they are liable for the relocation if a con-
          flict exists. It is a lot easier to move it on paper, with a pencil and eraser, than in the field
          once installed. Three-dimensional AutoCAD drawings greatly facilitate the coordination
   293   294   295   296   297   298   299   300   301   302   303