Page 154 - Well Control for Completions and Interventions
P. 154

146                                Well Control for Completions and Interventions


          Table 4.1 Initial test requirements
          Component to be       Recommended       Recommended
          tested                pressure test     pressure test
                                Low pressure (psi)  High pressure (psi)
          Annular preventer
          • Operating           200 300           Minimum of 70% of annular
            chambers            N/A                 BOP working pressure
                                                  Minimum of 1500
          Ram preventer
          • Fixed pipe          200 300           Working pressure of ram BOPs
          • Variable bore       200 300           Working pressure of ram BOPs
          • Blind/blind shear   200 300           Working pressure of ram BOPs
          • Operating chamber   N/A               Maximum operating pressure
                                                    recommended by ram BOP
                                                    manufacturer
          Choke line and        200 300           Working pressure of ram BOPs
            valves
          Kill line and valves  200 300           Working pressure of ram BOPs
          Choke manifold
          • Upstream of last    200 300           Working pressure of ram BOPs
            high-pressure valve  200 300          Optional
          • Downstream of last
            high-pressure valve
          Blow out prevention control system
          • Manifold and BOP    N/A               Minimum of 3000
            lines               Verify precharge  N/A
          • Accumulator         Function test     N/A
            pressure            Function test     N/A
          • Close time          Function test     N/A
          • Pump capability
          • Control stations
          Safety valves
          • Kelly, kelly valves,  200 300       Working pressure of component
            and floor safety
            valves
          Auxiliary equipment
          • Mud/gas separator   Flow test         N/A
          • Trip tank, flow     Flow test         N/A
            show
          As per API RP 53 (Table 1).