Page 155 - Well Control for Completions and Interventions
P. 155
Well Control Surface Equipment 147
Table 4.2 Initial test requirements
Component to be Recommended Recommended
tested pressure test pressure test
Low pressure (psi) High pressure (psi)
Annular preventer
• Operating 200 300 Minimum of 70% of annular
chambers N/A BOP working pressure
N/A
Ram preventer
• Fixed pipe 200 300 Greater than the maximum
• Variable bore 200 300 anticipated surface shut-in
• Blind/blind shear 200 300 pressure
• Operating chamber N/A Greater than the maximum
anticipated surface shut-in
pressure
Greater than the maximum
anticipated surface shut-in
pressure
Diverter flowlines Flow test N/A
Choke line and 200 300 Greater than the maximum
valves anticipated surface shut-in
pressure
Kill line and valves 200 300 Greater than the maximum
anticipated surface shut-in
pressure
Choke manifold
• Upstream of last 200 300 Greater than the maximum
high-pressure valve Optional anticipated surface shut-in
• Downstream of last pressure
high-pressure valve Optional
Blow out prevention control system
• Manifold and BOP N/A Optional
lines Verify precharge N/A
• Accumulator Function test N/A
pressure Function test N/A
• Close time Function test N/A
• Pump capability
• Control stations
Safety valves
• Kelly, kelly valves, 200 300 Greater than the maximum
and floor safety anticipated surface shut-in
valves pressure
(Continued)