Page 22 - Failure Analysis Case Studies II
P. 22

9



























                       levels HL for the first leak and different ratios of sloshing (d* = 6/D) are assumed, it can be seen
                       from Fig. 9 that the silo must have been filled to the top, and the liquid must have sloshed relatively
                       far after hitting the ground to have produced the observed pattern on the site.


                                                     4.  CONCLUSIONS


                           Thc visual  inspection at the  site of  the  accident showed  the  typical picture  of  failure by
                            overpressure. Indications of an explosion or a chemical reaction, which could have produced
                            the overpressure, were not found. A pressure above atmospheric pressure can also be excluded
                           because the necessary safety devices were installed and operative.
                           According to the manufacturer of the silo, it was permissible to fill the silo with liquid up to
                            the seventh ring (counted from the bottom), i.e. ca 10 m high.
                            The amount of 407 t, admitted by the user, corresponds to a filling height of ca 14m.
                           The assessment of the filling height from the observed spurting distance also points to a filling
                            level practically at the top of the silo.
                           The design, manufacture  and  assembly of  the  silo can  be judged  as proper,  suitable and
                            according to normal engineering practice.
                           Tests on the material also indicate a higher level than  the seventh ring (counted from  the
                           bottom). This is supported by the observed deformations in the failed bolted joint of the silo.
                           An additional argument against the statement of the user related to the filling level is the fact
                           that the silo was still filled to the middle of the tenth ring (counted from the top), although
                           the whole neighbourhood was covered with slurry from the silo.
                            Based on these findings it can be said that failure of this silo was caused by filling it to too
                           high a level with liquid instead of forage.
                           It cannot be completely excluded that a mix-up in the way of counting the rings has contributed
                           to  the failure. Whereas one would  normally count  the rings starting from  bottom,  as for
                            buildings, the manufacturer of the silo counts the rings starting from top, because the silo is
                           erected that  way, assembling first the top,  then  putting rings under  the top ring until  the
                           intended height of the silo is reached.

                       Acknowledgemenf-The  calculations  were performed by  R. Primas, Section  Materials and  Structural MechdnicsiJoining
                       Technology of EMPA.
   17   18   19   20   21   22   23   24   25   26   27