Page 849 - Industrial Power Engineering and Applications Handbook
P. 849

System voltage regulation 24/803
        network  is being fed by more than one generator. When   by switching in or switching out a few units. In manual
        any transient fault occurs, the current flow through the   switching it will  be possible only in  steps. and may
        fault will be shared more by  the machine nearest to the   not  provide  a  smooth  compensation  and  may  also
        fault and less by  the one installed a little away. This will   cause switching transients (Section 23.5. I). Moreover.
        upset  the earlier tandem operation of the machines and   conventional switching methods (mechanical switching
        they will become unequally  loaded and may fall out of   through contactors and breakers), are sluggish due to
        step. The one near  the fault will  slow down more than   the time of closing and interruption, which may be ;is
        the other. The machine that shares the smaller amount of   much  as  three  or  four  cycles,  depending  upon  the
        the  load  will  slow down less and feed more, becoming   type of  interrupter (Section  19.5 and Table  19. I) as
        overmessed. Now it will  slow down and the other will   well as the minimum time required  for the discharge
        pick up. The situation will reverse thus and so the situation   of  the  capacitors. Human  sluggishness may  also
        will  continue creating  a  hunting  effect. The following   introduce some delay. They are therefore ill-suited to
         may  result  depending  upon  the transient  stability limit   meet the  system’s rapidly fluctuating needs.
        of the  system.                                    However, power systems that cater to almost fixed
                                                         loads  at  a  time and  whose  variations  occur  only  at
          The fault is cleared promptly and the normal condition   specific  times  of  the  day  may  not  require  ii  fast
          is restored. The setting and the speed of the protective   response. In such cases. it is possible to provide manual
          relays  should be  commensurate with such a situation   switching  methods  which  will  give  enough  time
          and isolate the  faulty  circuit as quickly as possible.   between two switchings. Manual switching, however,
          If  not,  the  machine  being  loaded most  may  fall  out,   has  certain  shortcomings,  due to  the  human  factor
          which may not  necessarily be the one nearer the fault   such as its  accuracy  and diligence,  as  noted  above.
          or                                             The recommended practice is therefore to select fast
          The situation may have a cascading effect until all the   reactive controls as noted below.
          machines fall out, resulting in a total  blackout.   2   Static VAr compensators (SVCs)  Whenever a large
                                                         reactive  control  is  required,  the  SVC  is  always  a
          To achieve a better level of stability it is desirable that   preferred method. The static VAr controllers are more
        the line be loaded a liltle less than the optimum power it   expensive, but  respond very  quickly. They cause no
        is  capable of  transmitting  to  sustain the  system  distur-   switching  transients  and  limit  the  magnitude  of  a
                                                         disturbance.  through  extremely  fast  controls. They
        bances  such  as  load  tluctuations, faults  and  switching
        of  large  machines  without  an outage. The  load curves   can handle large currents and peak  inverse voltages,
        (Figure 24.20) provide a guide to determine the level at   except voltage transients, such as switching surges or
                                                         lightning strikes, which may have a front time as low
         which  the line should be operated and from this can be   as  1-2  ps only (Section  17.3.3) while the  switching
         assessed the magnitude of di$turbances that the line can   time of a static device (a thyristor) may be as much as
         safely sustain and recover promptly without an outage.   one cycle, as discussed later. But surges can be taken
         Series reactive support will become essential. whenever
        the line loading is expected to be more than the STL, P,,   care of  by  a  surge arrester.  The use of  an  SVC or a
         (generally on  132  and  220  kV  networks).  But  series   manual  switching  will  largely  depend  upon  the
        reactive  support  has  been  found  extremely  useful  on   characteristics of the line. the type of load it is feeding
        existing lines even  up to  I  I  kV,  which  are required to   and  its  importance. For a  system having almost  the
        cater  for  higher  power  demands  than  were  originally   same type  of  load  demand  during  the  day.  inanual
        en\,i\aged.                                      switching  may  serve the  purpose.  But  for a  system
                                                         with wide fluctuations, an SVC alone will be suitable.
                                                         The  decision  will  vary  from  one system  to  another
        24.10  Switching of large reactive               and the system engineer can make a better choice.
                banks                                    /vote
                                                         If  auto-control  is selected through p.f. or voltage control. cate
        The \cries  capacitors are connected  in  series  with  the   must  be  taken  against  frequent  switchings  of  the  capaciroi-s
         power lines to provide reactive control to an individual   when  the  load  is  of  a  varying  nature  which  may  c;iuse  the
         load  or to a power distribution or transmission  system.   capacitors  also  to  switch frequently.  Fast  switching?, can  be
        They are therefore switched with the power lines and are   made possible by providing  special di\charyc devices. and by
                                                         controlling the number of switchings to within permisyihle limit\
        thus permanently connected devices.              (Section 26.1.1(2) by carefully arranging the unity 21.;  diicus\ed
          But the shunt capacitors can provide reactive control   in  Section 23. IS. 1
        through unswitched,  i.e. permanently  connected, banks
        (fixed VAr)  or through  switched banks  (variable VAr).   In SVCs the number of switchings is of no relevance,
        The unswitched VAr may be used to aid stability against   as they  are  free  from  inrush  currents.  Switching  is
         possible  overvoltages  of  the  network,  during  a  load   performed  at  the  instant  when  the  current  wave  is
         rejection  or an  open  circuit while the  switched  VAr  is   passing  through  its  natural  zero.  Static  devices  in
         used to maintain the level of p.f. during load variations.   various combinations  and feedback control systems,
         VAr  switching can be done in two ways.         which  may  be  computer-aided,  can  almost
                                                         instantaneously  (5 1 cycle) generate or absorb reactive
         I  Manual control  This is through switching devices   power, as may be demanded by the system. Correction
   844   845   846   847   848   849   850   851   852   853   854