Page 845 - Industrial Power Engineering and Applications Handbook
P. 845

System voltage regulation  24/799
           conditions, and the remainder are switched. Moreover,   Note
            switchable  reactors  are  switched  only  during  a   On  66 kV networks the  MVAr loading is normally high and
           temporary disturbance, therefore they have no adverse   therefore one  practice is to install MVAr meters  and adopt a
           effect  on  Po.  Ideally  they  can  be  made  fixed  to   manual  switching  during  variation  of  MVAr  beyond  the
           compensate 50-60%  of C,  and the remainder switched   permissible level, purely as a cost consideration.
            in  a  few  steps. The  size  and  number  of  steps will
           depend upon the likely underloading, open-circuiting   3  Series capacitors  These  are  used  for  line  length
           during offpeak periods or other temporary disturbances.   compensation  to  help  transmit  power  over  long
           The overvoltages that may occur under such conditions,   distances and also improve the stability level  of the
            and which must be controlled through these reactors,   network. They are usually installed at the line ends or
            is  a  matter  of  system  design  practice  adopted  by  a   at the selected locations. They reduce Zo and enhance
            country or its central power authorities and may be   SIL, PO, and boost the receiving-end voltage.
           broadly based on our discussions in Section 24.6 and
           Table 24.3. To determine more accurate overvoltage   Example 24.3 Application of  series compensation on
           conditions,  however, a TNA or EMTP study would   an HT distribution network
            be better for an existing system and earlier data and   Let us consider the primary distribution network of  Example
                                                        23.2 as shown in Figure 24.25(a) feeding an LT load of 29.4
           experience for a new system.                 MW at 0.98 p.f. through a 33/0.4 kV transformer. The following
                                                        line parameters have been considered:
           Note                                          Resistance of primary distribution overhead lines, section
           On  132 kV networks the MVAr loading is light. as most of the   B-B  at the operating temperature,
           p.F.  is controlled at  the  distribution level and  the  capacitive
           chargiiig MVAr demand is low (Table  24.2,  column 9). The   Ro = 0.13 akm per phase
           charging MVAr is normally not compensated because, on load,   Inductive reactance of  this section at 50 Hz
            more than this is offw by the load p.f.
                                                        XLo = 0.4 akrn per phase
           Shunt capacitors  These are used to supplement the   There is no leakage capacitance, C,,  and hence no Ferranti
           natural  line capacitance,  C,,  under  heavy  inductive   effect on such low voltages. We will use series compensation
            loading depending upon  the system voltage, but  are   to  reduce the  line voltage  drop and improve the  regulation
           used  generally  for p.f.  improvement of  the  system,   and  hence the  stability  of  the  network  as  well  as  its load
           where the natural C, is not sufficient to maintain the   transfer capability,
           line  p.f.  They  reduce  Z,  and  enhance SIL, Po, and   Load p.f. = 0.98 (L - 11.48')
           boost  the  line  voltage. They  are normally  switched
           and  not  permanently  connected to  avoid  resonance   In Example 23.2 the system was not capable of  transmitting
           on  load  rejection or an open circuit. Generally they   its full  capacity. Let us consider that with the  use of  series
                                                        compensation  it can be fully loaded up to
           are used for systems up to 33 kV, i.e. at the distribution
           end. But when the p.f. IS not fully compensated at the   30 MVA x  0.98 = 29.4 MW.
           distribution end it can be compensated at the secondary   The impedance of  the transformer
           transmission level of 66 kV or 132 kV. Capacitors at
                                                           Z
            such  voltages  may  be  connected through  dedicated   z=Px  v,"      (from equation (13.3))
            transformers, as illustrated in Figure 24.24.   100   kVAx lo3
                                                          -  10
                         66 or 132 kV line                _-    33'  x 106
                                                           100   ~ O X
                                                                     lo6
                                                         = 3.63 R
                                                         For ease of calculation,  let us consider the impedance of
                    Dedicated                           the transformer as its leakage reactance, ignoring resistance
                    transformer                         and draw an equivalent circuit diagram as in Figures 24.25
                                                        (b) and (c). Assuming the  length of  the  primary distribution
                       I
                                                        line to be 15 km, the total line parameters will become
                Switching                                      XL  = 3.63 + 15 x 0.4 + 3.63
                                                                  = 13.26
                                                        and     R  = 0.13 x  15
                                         banks
                                                                  = 1.95 R
                                                        Receiving-end voltage before series compensation
                                                        To study the voltage fluctuation at the receiving-end with
                                                        fluctuations of loads, let us do so in terms of variation in
                                                        the transmitting-end voltage, assuming the receiving-end
         Figure 24.24  Use of  dedicated transformer to connect   voltage remains constant at 33 kV. We are doing this for
         capacitors on networks 66 kV and above         ease of calculation and for drawing the phasor diagram.
   840   841   842   843   844   845   846   847   848   849   850