CHAPTER 24      Buffer Profiles and Level Determination                         411


           FIGURE 24-4

           (A) Part lead-time distribution using MLT. (B) Part lead-time distribution using CLT.
           (C) Part lead-time distribution using ASRLT.
        A

          Number of Parts








                        10          20          30          40          50          60
                                          Lead Time Days
        B


          Number of Parts







                        10          20          30          40          50          60
                                          Lead Time Days

        C

          Number of Parts








                       10           20          30          40          50          60
                                          Lead Time Days

        on its combination of attributes. Within that naming code, the first letter signifies part
        type, either M for make, B for buy, or D for distributed. Next is the variability category, 1
        for low, 2 for medium, or 3 for high. Next will be the lead-time category, 0 for short, 1 for
        medium, or 2 for long. Finally, the buffer profile name will be appended with an MOQ if
        a significant MOQ exists. For example, a distributed part with medium variability and
        short lead time is in the buffer profile D20. A purchased part with high variability, long
        lead time, and a significant MOQ will be in the buffer profile B32MOQ.