CHAPTER 24      Buffer Profiles and Level Determination                         417


                                   Buffer Level Examples

        To help illustrate the application of buffer level determination, three examples are pre-
        sented: one purchased, one manufactured, and one distributed.


             First Example: Purchased Part 403P    Part 403P will follow the buffer profile
        B11MOQ. The purchasing lead time for this part is 21 days. The ADU is 17. The MOQ is
        300. The MOQ represents 84 percent of usage over lead time. This is a medium-lead-time
        category part, so the MOQ is significant. The MOQ of 300 will be the green zone. The yel-
        low zone will be an entire lead time’s usage (17 units/day   21 days   357 units). The
        red zone will be calculated by combining the red zone base and safety factors. For red
        zone base 403P is in the medium-lead-time category (41 to 60 percent usage over lead
        time). In this particular case, we will use 50 percent (once again, this is determined by the
        planners for the specific environment). Red zone base will be 179 (357   0.5   178.5). For
        red zone safety, 403P is in the low variability category (20 to 40 percent of red zone base).
        In this particular case we will use 30 percent. Red zone safety will be 54 (179   0.3
        107.1). The top limit of the buffer (top of green) will be 890 units, top of yellow will be
        590, and top of red is 233. Figure 24-14 presents the buffer summary.

             Second Example: Manufactured Part 707    Part 707 will follow the buffer profile
        M21. The ASRLT for this item is 13 days. The ADU is 6. There are no ordering policies for
        the item. Part 707 is a medium-lead-time part. This will define both the green zone and
        red zone base at a range of 41 to 60 percent usage over lead time. In this environment, the
        planners chose to set this at 45 percent. The green zone for Part 707 will be 35 (78   0.45
          35.1). Red zone base also will be 35. Yellow zone will be set to usage over one full lead
        time: 78. For red zone safety, Part 707 is in the medium variability category (41 to 60 per-
        cent of red zone base). Planners have set this at 50 percent. Red zone safety will be 18 (35
          0.5). The top of green will be 166 units, top of yellow is 131, and top of red is 53. Figure
        24-15 presents the buffer summary.



           FIGURE 24-14

           Part 403P buffer summary.

          Part: 403P       Buffer                       233             590           890
          Lead Time: 21    Profile:
          Days             B11MOQ
                                          403P
          Green Zone       300                      R            Y              G
          Yellow Zone      357
          Red Zone Base    179                0%      20%     40%     60%      80%    100%
          Red Zone Safety  54