354 Practical Power System and Protective Relays Commissioning
FIGURE 20.6.5 Primary injection of reference circuit F1 and bus section Bus Section (BS).
4. Trip test
This test measures the operating time of BBProt, including trip relays
time, and measures the overall operating time to trip the CB practically
in the BBProt scheme.