Page 269 - Sustainability in the Process Industry Integration and Optimization
P. 269

246   Cha p te r  T e n


                     FIGURE 10.27         Q H,min  = 37.5 MW
                     Grand Composite   T [°C]
                     Curve for
                     Problem 7(b),
                     ΔT  = 30°C.     150
                       min
                                     100

                                      50
                                          Q Cmin =86.5 MW
                                       0
                                        0          50        100        ΔH [MW]




                     FIGURE 10.28     T [°C]  MP steam 37.5 MW
                     Appropriate
                     placement of
                     utilities for     150
                     Problem 7(c).
                                       100

                                            Cooling Water
                                        50   62.5 MW        Chilled Water 24 MW

                                         0
                                          0         50        100      ΔH [MW]



                       Answer to (d)(1). The flue gas heating option will probably be more expensive
                       than heating with steam. The temperature levels in the problem do not suggest
                       exploitation of furnace heat.
                       Answer to (d)(2). The appropriate placement of a heat pump is across the Process
                       Pinch, so the pump will transfer heat from below to above the Pinch. In this
                       problem it is technically impractical to install a heat pump with water or steam
                       as a working fluid, since this would require operation at a slight vacuum (the
                       Pinch is at 170°C/140°C). The relatively small duties that could be achieved
                       with this technique indicate that investment in a heat pump here is likely to be
                       economically unattractive.
                       Answer to (d)(3). Introducing a new steam level at a steam temperature of 165°C
                       is a good option that can be exploited by passing the steam (taken at 200°C)
                       through a steam turbine. This has the potential of generating additional power
                       on the site. The steam would be returned to the process at the level of 165°C
                       (the process heating requirement is at 150°C, which makes this arrangement
                       feasible). If the site could use additional power, then this option may reduce the
                       overall utility cost by providing on-site power generation.
   264   265   266   267   268   269   270   271   272   273   274