Page 277 - Sustainability in the Process Industry Integration and Optimization
P. 277

254   C h apter  Ele v e n


                                 400
                                              ΔT min  = 11.50°C
                                 300
                               Temperature [°C]  200




                                 100

                                  0
                                                 1             2
                                                Enthalpy [MW]

                     FIGURE 11.1  Composite Curves of FCC process with optimum ΔT  (after
                                                                    min
                     Al Riyami, Klemeš, and Perry, 2001).

                     17.5°C for constant α. The area efficiency α of the existing network
                     was found to be 0.804. This value indicated that the existing design
                     was using the area reasonably efficiently. Even so, there was still room
                     for  improvement. Since the constant-α targeting produced a
                     conservative estimate, an incremental α value of 1.0 was used to set
                     the retrofit target, which yielded potential for energy savings of
                     about 12.117 MW. Analysis of the existing design revealed that there
                     were four process-to-process heat exchangers that transferred heat
                     across the Process Pinch (from above to below the Pinch). It was
                     also found that some heaters supplied utility heat to process streams
                     below the Pinch and that some coolers removed heat from process
                     streams above the Pinch. These energy violations of the established
                     Pinch rules generated the scope of the project’s possible energy
                     savings.
                        The retrofit design using the Network Pinch method allowed a
                     limit to be set on the structure’s energy recovery. The next stage
                     consisted of testing a set of modifications that would result in higher
                     levels of energy recovery in the process. The increase in energy
                     recovery would come at the expense of increased heat exchange area.
                     Therefore, any benefit in energy cost reduction had to be weighed
                     against the additional capital cost associated with increasing that
                     area. A number of promising design solutions were generated, which
                     were then optimized for minimum total cost. The four designs
                     identified each involved a payback period of less than two years, yet
                     increases in energy prices rendered the actual payback period closer
                     to one year. The final design chosen for the retrofit situation was the
                     one with the shortest payback period and the least additional area
                     required; it is shown in Figure 11.2.
                        In this design option, four new heat exchangers were added and
                     one existing exchanger (number 1 in Figure 11.2) was removed, since
                     its duty approached zero. In reality the exchanger equipment item
   272   273   274   275   276   277   278   279   280   281   282