Page 147 - How To Implement Lean Manufacturing
P. 147

How to Do Lean—The Four Strategies to Becoming Lean         125


                    The Present Case Analysis
                    Let’s analyze the chart for the three simple reviews available from this type of a graph,
                    specifically.
                       This line balance chart shows graphically the time wasted, which is the distance from
                    the top of the bar graph for any station to the takt line—that is, if the production could be
                    made at takt rate. You will find in Chap. 16 that this cell is performing so poorly it takes
                    over two shifts, rather than the design of one shift, to produce the volume. So even
                    though this graph shows clearly there is a huge time waste, it also grossly understates
                    the waste. The actual wasted work time is much worse than this chart shows, and this
                    chart is very bad! (The actual paid time was over 78 seconds per unit × 10 operators or
                    780 seconds, yielding 623 seconds per unit of waste; over 80 percent wasted labor time.)
                       The balance is poor since the tallest bar is 22 seconds and the shortest is 10. This is
                    not good balance; the cycle times should be very similar. The bottleneck, the longest
                    cycle time, occurs twice. Both stations 1 and 6 are 22 seconds.

                    The Redesign: Synchronize to Takt
                    Next, we rebalanced to takt by redistributing the work at the work stations. Recall
                    that there were 157 seconds of work and we need a takt of 39 seconds, which yields:
                    157 seconds of work ÷ 39 seconds/station = 4.02 theoretical stations. With one person
                    per station, we can’t have 0.02 persons, so we will check out five stations, which gives
                    us 157 ÷ 5 = 31 seconds per station. And if OEE is 90 percent, we could design for a
                    cycle time of 39 × 0.90 = 35 seconds. This will work as a starting point. So our balance
                    will be based on five operators and a design cycle time of 35 seconds.
                       With that in mind, we redistribute the work as shown in Figure 7-4.

                                     Zeta Cell, Original Design           New Balanced Proposal
                                         10 Operators                         5 Operators
                                  Operator                Final  Time per  New design, Time per
                                   No.      Work element  time  operator  operator No. operator
                     Step no  FC Id.
                       1     10     1   Cut bracket         3              1
                       2     20     1   Assy bushing (3)   12     22       1
                                                                                  31
                       3     30     1   Install o-ring and clip  7         1
                       4     40     2   Place in jig, glue  9              1
                                                                  15
                       5     50     2   Press in magnets (2)  6            2
                       6     60     3   Insert o-rings, cap, grease  13  13  2
                                                                                  35
                       7     70     4   Install support     8              2
                                                                  16
                       8     80     4   Install o-ring and clip (2)  8     2
                       9     90     5   Apply epoxy, 3 locations  14  14   3
                       10   100     6   Install control capacitor  8       3      28
                       11   110     6   Apply epoxy, topside  6   22       3
                       12   120     6   Install retainer ring  8           4
                       13   130     7   Install cover cap   7              4
                                                                  10              33
                       14   140     7   Unload/load machine (2)  3         4
                       15   150     8   Apply final sealant (1)   15  15   4
                       16   160     9   Final test, wrap leads  18  18     5
                                                                                  30
                       17   200     10  Package            12     12       5
                                        Total              157   157              157
                    FIGURE 7-4  Zeta cell rebalancing calculations.
   142   143   144   145   146   147   148   149   150   151   152