Page 460 - Industrial Power Engineering and Applications Handbook
P. 460

14/434  Industrial Power Engineering and Applications Handbook
        hypothesis. It is therefore imperative that the minimum   than 3 m from all sides through a square shaped nozzle
        peak current according to the multiplying factor,  shown   of  a  capacity  of  30  Omin  *lo%  at  a  pressure  of  46
        in Table 13.1 1, is obtained during the course of the test   N/cm'  +IO%  and a spray angle of  60-80".  (See Figure
        itself, for example a minimum of 2.1 x 50, i.e.  105 kA in   14.9). The rate  at  which  the water  is impinged  on the
        the above test. The multiplying factor will correspond to   surface under test should be almost 5 mdminute. Standard
                                                       nozzle designs are also available which can ensure the
        the specified fault current, (50 kA) and not the test current,   desired  quantity  of  water  at  a pressure of 46 N/cm2 *
        e.g. 47 kA in the above test. If during the course of the
         test, the peak  making current is  less than  this, the test   10%. Kefer to IEC 60298.
         will be considered invalid.                     For a uniform  spray on the entire test surface  more
                                                       nozzles may be employed. Normally, surfaces of up to a
         14.3.8 Verification of the protective circuits   width of 3 m may be tested at a time. For larger widths
                                                       the test may be conducted in two steps. Normally, only
         All  protective  circuits  must  be checked  for continuity   one vertical surface is tested at a time. Besides the vertical
         and the operational and sequential requirements, if  any,   sections, the test will  also be conducted on:
         in addition to the following:
                                                         The roof  surface, from  nozzles  located at  a suitable
          Checking for the grounding of instrument transformers   height
          by means of a low-voltage source (1 0 V or so) using   0  The floor  outside the enclosure for a  distance up to
          a bell, buzzer or a light.
                                                         1  m in front of the switchgear assembly, the assembly
         0  Control wiring insulation test, as in Table 14.3.   being in its normal  position.
          Polarity  test:  to  check  the  connections  through  the
          potential  transformer  to  ensure that  the  connections
          between the transformer and the meters or relays have   Figure  14.9 illustrates the above requirements.
           a correct relative polarity. Otherwise the meters would
           show erratic readings, while the relays would transmit   Test results
           wrong signals. This test may also be conducted with a   The test  may be considered successful if
           low-voltage source of 10 V by observing the deflection
           of the instruments.                           No water droplets can be observed  on the insulation
                                                         of the main  and auxiliary circuits
         14.3.9 Verification of clearance and creepage   There are no water droplets on the electrical components
               distances                                 or mechanism of the equipment
                                                       0  There is no significant accumulation of water on any
         The clearances may be verified as in Table 28.4, whereas
         for creepages Table 28.5 may be followed.       part of the structure or other non-insulating parts. This
                                                         requirement is to minimize corrosion.
         14.3.10  Verification of degree of protection                                3
         Enclosure test
         The types and degrees of enclosure protection are generally
         the same as defined for motors in  Section  1.15, Tables
         I. 10 and 1.1 1. The testing requirements and methods of
         carrying out such tests are also almost the same as for
         motors, and as discussed in Section  11.5.3.

         Weatherproof test
         This  test  is  applicable  to  all  outdoor  metal-enclosed   Platform ~
         switchgear and controlgear assemblies, as in IEC 60298,
         IEC  60694  and ANSI C-37/20C. The enclosure  to  be   F
         tested  should be complete in  all  respects  including  its   GL   D
         mounts, bushings (for HT switchgear assemblies, 1 kV   zz=K-r
         and above) and wiring. One or more vertical units can be
         tested simultaneously as may be convenient, but not more
         than  3  m  panel  width  can  be  tested  at  a  time.  For  a
         multiple unit switchboard, however, at least two vertical
         units should be tested together to check the joints between
         the units.
                                                                   = 2.5 to 3.0 rn
         Procedure                                          I  D  I                         I
         All  surfaces or the enclosure must be tested uniformly   Minimum heiaht above floor  level
         for 5 minutes each. The water will  be impinged on the
         surface  of  the  enclosure from a  distance of  not  more   Figure 14.9  Arrangement for weatherproofing test
   455   456   457   458   459   460   461   462   463   464   465