Page 455 - Industrial Power Engineering and Applications Handbook
P. 455

Testing of  metal-enclosed switchgear assemblies  14/429

        3  Other parts of the switchgear assembly and the auxiliary   The test conditions as noted above may over-estimate
           components,  for  which  limits  have  been  specified,   the  rise  in  temperature  during  actual  operation. Some
           will  not  exceed  the  hot  spot  temperature  rise,  as   latitude may therefore be considered while analysing the
           recommended  in Table  14.5.                final results if the temperature rise thus estimated exceeds
                                                       the prescribed limits only marginally.
        Genercrl notes on testing procedure
          The main bus through its entire length is fed with its   14.3.6 Verification of short-circuit strength
          rated  current,  while  in  operation  it  would  carry  a
          diminishing value after every feeder or a sectional bus.   This  test  is  conducted  to  verify  the  suitability  of  the
          The sectional bus is fed similarly.          equipment to withstand a prospective short-circuit current
          If  a control  bus  is  also used  add for its heat  loss. A   that may develop on a fault. It may  also be termed the
          third  current source may be required if  a temperature   steady state symmetrical  fault current ISc  or the  short-
          rise in this bus is also desired.            time (withstand current) rating of the equipment. When
          Keep the control circuits energized if possible, to further   the equipment is an interrupting device, it is referred to
          save on calculations and to obtain more accurate results.   as its symmetrical breaking current.
          In the sample calculations as shown in Table  14.4 we   It is permissible to test just one panel of a multi panel-
          consider this in a de-energized condition for the sake   assembly  so  long  as  the  construction  of  other  panels
          of  more clarity.                            is similar and busbar arrangement  and supports are the
          Each feeder is considered at its optimum rating, based   same. The value of the prospective short-circuit current
          on the current rating of the motor or the rating of the   may be determined from a calibrated oscillogram. The
          power fuses in a SFU or FSU feeder while the current   test  current in any phase should not vary by more than
          may  be much less in actual operation.       10%  of  the  average  in  the  three  phases  and  must  be
          If the temperature rise, as determined above. exceeds   applied for a predetermined time of  1 or 3 seconds. Unless
        permissible  limits it  will  be  desirable  to provide  extra   specified otherwise, this should be considered as to be  1
        louvres, a forced cooling arrangement, larger busbars or   second.
        a  change  in  their  configuration  whichever  is  more   The oscillogram must reveal continuity of the current
        convenient and easy to implement.              during the test period. The frequency of the test  circuit
                               Q  "








                                                      L
         0 Short circuit generator
         @ Circuit breaker
         @ H.T. transformer
         @ Master breaker
           To  isolate the circuit after the test is over and to also interrupt the test in
           between,  in  case  the  test  piece fails.  The  breaker  must  possess an
           instantaneous capacity of more than the test current and the short-circuit
           MVA of the feeding generator. To achieve the desired voltage it must be
           suitable to perform the duties of  repeated short-circuit tests.
         @ Switch (to perform the making and breaking duties during the test)
         @ Source side reactance 'L (to control the magnitude of the test current)
         @ Source side resistance 'R' (to control the p.f. as per the test  requirements)
         @ High current  step down transformer
         @ Test object
         @ Current shunt
         @ R-C  voltage  dividers
         @ Recording instruments:
           EM0 :  Electro-magnetic oscillograph, to record power frequency quantities   CRO :  Cathode ray oscillograph, to record voltages of  a
                such as short  circuit  average  and peak currents in each phase,   transient  nature. For instance, re-striking voltages
                voltage across each  phase during and after  the test, generator   (TRVs), whose frequency of  oscillations  is beyond
                voltage and time duration of test, as recorded in Figure 14.4   the response range of  EMO.
                         Figure 14.3  General arrangement of a power circuit to conduct a short-circuit test
   450   451   452   453   454   455   456   457   458   459   460