Page 643 - Industrial Power Engineering and Applications Handbook
P. 643

18/608  Industrial Power Engineering and Applications Handbook
       Table 18.5  Determining TOV

       TOVs    Cause of TOV              OVjactor   Tripping time      TOVfacror Kyrom Figure 18 16(b) for a
                                                                      purticular brand of  surge arrester
                                                                      ~~                     ~
                                        ~
       TOV,"   Ground fault
               (i)  for a solidly grounded  system   5 1.4   1 or 3 seconds   1.16 - for  1 second
                                                                       I. I3 - for 3 seconds
               (ii)  For an isolated neutral system   1.73   IO seconds to a few   1.1  ~  for  IO seconds
                                                  hours and more       0.93  ~  for 2 hours
       TOV,    Load rejection            1.1       1 second            1.16
       TOV,"   Phase-to-phase  fault     h         1  or 3 seconds     1.16-forlsecond
                                                                       1.13 - for 3 seconds
       "Consider only one eventuality  to occur at a time.
       bA phase-to-phase  fault is a transient condition and may give rise to TRVs in the healthy phase. Such a situation may exist for one to three
       seconds, depending upon the protection scheme adopted. It is a long-duration condition for a surge arrester. Such an occurrence may be rare
        and need not be considered  if the GF condition  is already taken into account. However, for the sake of accountability, the voltage rise in
       the healthy phase under such a fault condition may be considered  similar to the first pole-clearing condition of a circuit breaker. Although
        it may not be appropriate to equate the two conditions, the magnitude of overvoltage may fall in a similar range. IEC 60056 has suggested
       the following TRVs across the first pole during a brcaker-opening  sequence, while the other two poles are still in a cluaed condition:
        up to 72.5 kV  1.3 V,
        100-170  kV  1.3-1.5  V,
        245 kV and above 1.3 V,
        (V,  being the rated voltage of the system)
        The overvoltage factor, due to  a phase  fault,  may  thus not  exceed  a ground  fault (GF) condition. It would, therefore,  be  appropriate  to
        consider the GF condition  instead of a phase fault and, in all probability,  it will be adequate to account for this contingency.



         Duration:  This  will  depend  upon  the  ground  fault   and minimum rated voltage  V,, = 243/0.8 = 304 kV, when the
         protection scheme adopted and may be considered as   system is not subject to any TOV. Consider a solidly grounded
         follows:                                     system,  with  a  protective  scheme  of  3  seconds  and  the
          (a)  For a solidly grounded system: 1-3  seconds (nor-   eventuality of load rejection, which may occur simultaneously:
            mally,  generation  and  transmission  systems  are   :.  Total TOV = 1.4 x  1.1 = 1.54
            provided  with  a longer tripping  time  of  up  to  3   From Figure l8.16(b), the TOV factor, K= 1.13 for 3-second
            seconds, and a distribution system still longer, say,   tripping.
            up to  10 seconds).                                         243
          (b) For an isolated, impedance or resonant grounded   :.  Required V, =  1.54
                                                                      1.13
             system: from a few minutes to several hours (when   = 331 kV (which is higher than 304 kV)
            it is 2 hours or more, it may be considered conti-
             nuous for the purpose of selection of an arrester).
          Short-circuit condition (Section  13.4.1(6)).
          Based on these discussions and experience from diffe-
        rent installations, the likely power frequency overvoltage   t
        (TOV) over a long period of operation for different voltage
        systems can be determined. For a more accurate value at
        a  particular  installation,  it  is  advisable to  carry  out  a
        system study. Generally, not more than one contingency
        may occur at a time. However, depending upon the type
        of  system, which may be critical and more sensitive to
        load variations, a fault condition or frequent switchings,
        more than one contingency may also be considered.

        Example 18.3                                       0.01   0.1   1.0  Time -     1000   10000
                                                                                  100
                                                                             10
        For a 400 kV system
        V,  = 420 kV and                                       Curve - 1, No prior energy.
                                                               Curve - 2, With prior energy.
            420
        V,  = - 243 kV
                =
            45                                        Figure 18.16(a)  TOV  capability of a distribution class arrester
   638   639   640   641   642   643   644   645   646   647   648