Page 199 - Plant design and economics for chemical engineers
P. 199

COST  ESTIMATION  173

     instrumentation. This part of the capital investment is sometimes combined with
     the general equipment groups. Total instrumentation cost depends on the
     amount of control required and may amount to 6 to 30 percent of the purchased
     cost for all equipment. Computers are commonly used with controls and have
     the effect of increasing the cost associated with controls.
          For the normal solid-fluid chemical processing plant, a value of 13 percent
     of the purchased equipment is normally used to estimate the total instrumenta-
     tion cost. This cost represents approximately 3 percent of the total capital
     investment. Depending on the complexity of the instruments and the service,
     additional charges for installation and accessories may amount to 50 to 70
     percent of the purchased cost, with the installation charges being approximately
     equal to the cost for accessories.


     Piping
     The cost for piping covers labor, valves, fittings, pipe, supports, and othe ‘terns
                                                                     +m is
     involved in the complete erection of all piping used directly in the process.
     includes raw-material, intermediate-product, finished-product, steam, water, air,
     sewer, and other process piping. Since process-plant piping can run as high as
     80 percent of purchased-equipment cost or 20 percent of tied-capital invest-
     ment, it is understandable that accuracy of the entire estimate can be seriously
     affected by the improper application of estimation techniques to this one
     component.
          Piping estimation methods involve either some degree of piping take-off
     from detailed drawings and flow sheets or using a factor technique when neither
     detailed drawings nor flow sheets are available. Factoring by percent of pur-
     chased-equipment cost and percent of fixed-capital investment is based strictly
     on experience gained from piping costs for similar previously installed
     chemical-process plants. Table 8 presents a rough estimate of the piping costs
     for various types of chemical processes. Additional information for estimating

     TABLE 8
     Estimated cost of piping

                                           Percent of fixed-capital
                   Percent  of  purchased-equipment  investment
     Type  of
     process plant  Material  Labor  Total       Total

     Solid  t         9       7      16            4
     Solid-fluid $   17      14      31            7
     Fluid  0        36      30      66           13
     t A coal briquetting plant would be a typical solid-processing plant.
     $ A shale oil plant with crushing, grinding, retorting, and extraction
     would be a typical solid-fluid processing plant.
     0  A distillation unit would be a typical fluid-processing plant.
   194   195   196   197   198   199   200   201   202   203   204