Page 200 - Plant design and economics for chemical engineers
P. 200

174  PLANT DESIGN AND ECONOMICS FOR CHEMICAL ENGINEERS

         TABLE 9
         Component electrical costs as percent of total
         electrical cost

                                                       Typical
         Component                    Range, %         value, %

         Power wiring                 25-50            40
         Lighting                      I-25            1 2
         Transformation and service    9-65            40
         Instrument  control  wiring   3-8              5
         The lower range is generally applicable to grass-roots single-product plants;
         the higher percentages apply to complex chemical plants and expansions
         to major chemical plants.



         piping costs is presented in Chap. 14. Labor for installation is es ‘mated as
         approximately 40 to 50 percent of the total installed cost of piping. Mat  ial  and
                                                                     \
         labor for pipe insulation is estimated to vary from 15 to 25 percent of the total
         installed cost of the piping and is influenced greatly by the extremes in
         temperature which are encountered in the process streams.


         Electrical Installations
         The cost for electrical installations consists primarily of installation labor and
         materials for power and lighting, with building-service lighting usually included
         under the heading of building-and-services costs. In ordinary chemical plants,
         electrical-installations cost amounts to 10 to 15 percent of the value of all
         purchased equipment. However, this may range to as high as 40 percent of
         purchased-equipment cost for a specific process plant. There appears to be little
         relationship between percent of total cost and percent of equipment cost, but
         there is a better relationship to fixed-capital investment. Thus, the electrical
         installation cost is generally estimated between 3 and 10 percent of the fixed-
         capital investment.
              The electrical installation consists of four major components, namely,
         power wiring, lighting, transformation and service, and instrument and control
         wiring. Table 9 shows these component costs as ratios of the total electrical cost.


         Buildings Including Services
         The cost for buildings including services consists of expenses for labor, materi-
         als, and supplies involved in the erection of all buildings connected with the
         plant. Costs for plumbing, heating, lighting, ventilation, and similar building
         services are included. The cost of buildings, including services for different types
         of process plants, is shown in Tables 10 and 11 as a percentage of purchased-
         equipment cost and tied-capital investment.
   195   196   197   198   199   200   201   202   203   204   205