246 Industrial process plant construction estimating and man-hour analysis



              Example 12.4.3
              Engines and generators (B2)
                 Work Scope: Set engine, couplings, and generator
                 Facility—diesel power plant
                 Data for input:
                 x: 14, 280, and 280
                 y: 2792, 924, and 924


                      Engines, couplings, and generators (B2)  Quantity  MH
                      Engine generator set 296962#      14         2792
                      Spring element                    280        924
                      Anchoring plate with AB           280        924



                   3000
                  Man hour  2000  y = -7.0226x + 2890.3      Series1
                   1000
                              2
                             R  = 1
                      0                                      Linear (Series1)
                       0        100       200       300      Linear (Series1)
                                   Quantity
            FIG. 12.4.3 Engine, coupling, and generator.


                                          2
                 The coefficient of determination, R , is exactly +1 and indicates a positive fit
              (Fig. 12.4.3).
                 All data points lie exactly on the straight line. The relationship between X and Y
              variables is such that as X increases, Y also increases.



              Example 12.4.4
              Install pipe modules
                 Work scope: Install pipe modules (B3)
                 Facility—diesel power plant
                 Data for input:
                 x: 14, 112, and 224
                 y: 480, 600, and 840

                                                          Quantity  MH

                      Installation of pipe modules (B3) estimate  x  y
                      Pipe module                         14        480
                      Bellows                             112       600
                      Bellows (bolt up)                   224       840